Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisville |
---|---|
Assessment Year | 1998 |
Principal Product | Cold rolled steel shelves and baskets |
NAICS | n/a |
SIC | 3316 - Cold Finishing Of Steel Shapes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 12,000,000 Units |
Production Hrs. Annual | 6,000 |
Location (State) | KY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $146,986 | 5,115,182 | kWh | $0.03 |
Electricity Demand | $48,647 | 10,894 | kW-months/year | $4.47 |
Natural Gas | $124,284 | 35,031 | MMBtu | $3.55 |
TOTAL ENERGY COSTS | $342,020 | |||
RECOMMENDED SAVINGS* | $1,102,028 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Administrative Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Administrative Changes | Primary Raw Material | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,608 Cost: $6,654 |
$951 | 2,931 | $657 | 63 | - | - | - | - | - | - | - | - | - | - |
$951 2,931 kWh |
$657 63 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $647 Cost: $400 |
- | - | - | - | $647 | 187 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$647 187 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $4,112 Cost: $200 |
$974 | 109,320 | $3,138 | 218 | - | - | - | - | - | - | - | - | - | - |
$974 109,320 kWh |
$3,138 218 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $661 Cost: $1,128 |
- | - | - | - | $661 | 190 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$661 190 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $8,870 Cost: $2,300 |
- | - | - | - | - | - | - | - | - | - | - | - | $8,870 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
$8,870 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.8312 USE BUILDING MATERIALS WHICH REQUIRE LESS ENERGY TO PRODUCE |
Savings: $45,190 Cost: $106,250 |
- | - | - | - | - | - | - | - | - | - | $45,190 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$45,190 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5242 RECOVER METALS FROM SPENT SOLUTIONS AND RECYCLE |
Savings: $19,940 Cost: $90,000 |
- | - | - | - | - | - | $19,940 | 6,000 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$19,940 6,000 lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.432 CROSS-TRAIN PERSONNEL TO AVOID LOST TIME |
Savings: $1,000,000 Cost: $102,500 |
- | - | - | - | - | - | - | - | $1,000,000 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$1,000,000 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.451 ADD ADDITIONAL PRODUCTION SHIFT |
Savings: $21,000 Cost: $10,000 |
- | - | - | - | - | - | - | - | $21,000 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$21,000 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,102,028 Cost: $319,432 |
$1,925 | 112,251 | $3,795 | 281 | $1,308 | 377 | $19,940 | 6,000 | $1,021,000 | - | $45,190 | - | $8,870 | - | $1,925 112,251 kWh |
$3,795 281 kW-months/year |
$1,308 377 MMBtu |
$19,940 6,000 lb |
$1,021,000 - $ |
$45,190 - $ |
$8,870 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Administrative Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (haz) | Administrative Changes | Primary Raw Material | Ancillary Material Cost |