Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisville |
---|---|
Assessment Year | 1999 |
Principal Product | Bottling Distilled Spirits |
NAICS | n/a |
SIC | 2085 - Distilled And Blended Liquors |
Sales | $50,000,000-$100,000,000 |
# of Employees | 196 |
Plant Area (Sq.Ft.) | 152,160 |
Annual Production | 5,400,000 Pieces |
Production Hrs. Annual | 2,188 |
Location (State) | KY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $181,409 | 5,139,508 | kWh | $0.04 |
Electricity Demand | $24,137 | 16,445 | kW-months/year | $1.47 |
Natural Gas | $109,000 | 27,116 | MMBtu | $4.02 |
TOTAL ENERGY COSTS | $430,672 | |||
RECOMMENDED SAVINGS* | $27,640 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $15,248 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,210 Cost: $50 |
$2,715 | 77,081 | $495 | 336 | - | - | - | - | - | - |
$2,715 77,081 kWh |
$495 336 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,678 Cost: $261 |
$1,420 | 40,152 | $258 | 176 | - | - | - | - | - | - |
$1,420 40,152 kWh |
$258 176 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $594 Cost: - |
$594 | 16,706 | - | - | - | - | - | - | - | - |
$594 16,706 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $5,027 Cost: $4,475 |
- | - | - | - | $2,640 | 238,700 | - | - | $2,387 | - |
- - kWh |
- - kW-months/year |
$2,640 238,700 lb |
- - $ |
$2,387 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $7,011 Cost: $9,500 |
- | - | - | - | $1,086 | 98,760 | - | - | $5,925 | - |
- - kWh |
- - kW-months/year |
$1,086 98,760 lb |
- - $ |
$5,925 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $10,120 Cost: - |
- | - | - | - | - | - | $10,120 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$10,120 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $27,640 Cost: $14,286 |
$4,729 | 133,939 | $753 | 512 | $3,726 | 337,460 | $10,120 | - | $8,312 | - | $4,729 133,939 kWh |
$753 512 kW-months/year |
$3,726 337,460 lb |
$10,120 - $ |
$8,312 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $15,248 Cost: $14,025 |
$2,715 | 77,081 | $495 | 336 | $3,726 | 337,460 | - | - | $8,312 | - | $2,715 77,081 kWh |
$495 336 kW-months/year |
$3,726 337,460 lb |
- - $ |
$8,312 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | One-time Revenue or Avoided Cost |