IAC logo
IAC Assessment: UL2404
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UL2404
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Louisville
Assessment Year 2024
Principal Product Automotive Parts
NAICS 336370 - Motor Vehicle Metal Stamping
SIC 3465 - Automotive Stampings
Sales $100,000,000-$500,000,000
# of Employees 450
Plant Area (Sq.Ft.) 820,000
Annual Production 10,000,000 Pieces
Production Hrs. Annual 6,120
Location (State) KY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $508,117 17,753,900 kWh $0.03
Electricity Demand $755,054 36,302 kW-months/year $20.80
Electricity Fees $317,231 - $ -
Natural Gas $395,917 55,452 MMBtu $7.14
TOTAL ENERGY COSTS $1,976,319
RECOMMENDED SAVINGS* $419,079 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas
$ kWh $ kW-months/year $ $ $ MMBtu
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$50,786
Cost:
$33,072
- - - - $50,786 - - - -
-
kWh
-
-
kW-months/year
$50,786
-
$
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,084
Cost:
$419
$269 9,393 $815 39 - - - - $269
9,393
kWh
$815
39
kW-months/year
-
-
$
-
-
MMBtu
03: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP Savings:
$1,516
Cost:
-
$385 13,465 $1,131 54 - - - - $385
13,465
kWh
$1,131
54
kW-months/year
-
-
$
-
-
MMBtu
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$5,080
Cost:
$13,000
- - - - - - $5,080 711 -
-
kWh
-
-
kW-months/year
-
-
$
$5,080
711
MMBtu
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$4,523
Cost:
$13,000
- - - - - - $4,523 633 -
-
kWh
-
-
kW-months/year
-
-
$
$4,523
633
MMBtu
06: 2.2692 USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER Savings:
$5,809
Cost:
$43,234
$1,376 48,084 $4,433 214 - - - - $1,376
48,084
kWh
$4,433
214
kW-months/year
-
-
$
-
-
MMBtu
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,250
Cost:
$840
$1,250 43,660 - - - - - - $1,250
43,660
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
08: 2.4235 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES Savings:
$24,490
Cost:
$4,200
$10,095 352,959 $14,395 696 - - - - $10,095
352,959
kWh
$14,395
696
kW-months/year
-
-
$
-
-
MMBtu
09: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4,134
Cost:
$16,300
$4,134 144,541 - - - - - - $4,134
144,541
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
10: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$320,407
Cost:
$3,432,213
$135,179 4,726,522 $185,228 8,904 - - - - $135,179
4,726,522
kWh
$185,228
8,904
kW-months/year
-
-
$
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$419,079
Cost:
$3,556,278
$152,688 5,338,624 $206,002 9,907 $50,786 - $9,603 1,344 $152,688
5,338,624
kWh
$206,002
9,907
kW-months/year
$50,786
-
$
$9,603
1,344
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas