IAC logo
IAC Assessment: UM0107
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UM0107
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Michigan
Assessment Year 1998
Principal Product Water deflectors for automotive industry
NAICS n/a
SIC 2752 - Commercial Printing, Lithographic
Sales $10,000,000-$50,000,000
# of Employees 90
Plant Area (Sq.Ft.) 171,000
Annual Production 7,900,000 Pieces
Production Hrs. Annual 6,240
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $44,112 543,083 kWh $0.08
Electricity Demand $6,770 600 kW-months/year $11.28
Electricity Fees $9,988 - $ -
Natural Gas $10,570 2,079 MMBtu $5.08
TOTAL ENERGY COSTS $73,000
RECOMMENDED SAVINGS* $34,255 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Fees Solid Waste (non-haz) Primary Product Electricity Usage Electricity Fees Solid Waste (non-haz) Primary Product
$ kWh $ $ $ lb $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,746
Cost:
$3,572
$1,746 23,447 - - - - - - $1,746
23,447
kWh
-
-
$
-
-
lb
-
-
$
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$250
Cost:
$250
$250 5,275 - - - - - - $250
5,275
kWh
-
-
$
-
-
lb
-
-
$
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$7,179
Cost:
$250
- - $7,179 - - - - - -
-
kWh
$7,179
-
$
-
-
lb
-
-
$
04: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$130
Cost:
$100
- - - - $130 260 - - -
-
kWh
-
-
$
$130
260
lb
-
-
$
05: 4.4230 MOVE PRODUCT USING MECHANICAL MEANS Savings:
$10,400
Cost:
$2,250
- - - - - - $10,400 - -
-
kWh
-
-
$
-
-
lb
$10,400
-
$
06: 4.1220 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS Savings:
$14,550
Cost:
$5,200
- - - - - - $14,550 - -
-
kWh
-
-
$
-
-
lb
$14,550
-
$
TOTAL RECOMMENDED Savings:
$34,255
Cost:
$11,622
$1,996 28,722 $7,179 - $130 260 $24,950 - $1,996
28,722
kWh
$7,179
-
$
$130
260
lb
$24,950
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
$
-
-
lb
-
-
$
Savings
Cost
$ kWh $ $ $ lb $ $
Electricity Usage Electricity Fees Solid Waste (non-haz) Primary Product Electricity Usage Electricity Fees Solid Waste (non-haz) Primary Product