Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 1998 |
Principal Product | Forged Rings |
NAICS | n/a |
SIC | 3717 - |
Sales | $10,000,000-$50,000,000 |
# of Employees | 41 |
Plant Area (Sq.Ft.) | 93,000 |
Annual Production | 20,000,000 Pieces |
Production Hrs. Annual | 6,120 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $109,086 | 6,830,598 | kWh | $0.02 |
Electricity Demand | $228,124 | 15,192 | kW-months/year | $15.02 |
Electricity Fees | $(-5,332) | - | $ | - |
Natural Gas | $500,824 | 143,816 | MMBtu | $3.48 |
TOTAL ENERGY COSTS | $853,803 | |||
RECOMMENDED SAVINGS* | $53,356 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $24,693 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $364 Cost: $980 |
$202 | 6,155 | $162 | 22 | - | - | - | - | - | - |
$202 6,155 kWh |
$162 22 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $663 Cost: $2,419 |
$486 | 13,482 | $177 | 24 | - | - | - | - | - | - |
$486 13,482 kWh |
$177 24 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $364 Cost: $1,200 |
$202 | 9,379 | $162 | 22 | - | - | - | - | - | - |
$202 9,379 kWh |
$162 22 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $19,654 Cost: $4,350 |
- | - | - | - | - | - | $19,654 | 5,328,650 | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$19,654 5,328,650 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4155 METER WASTE WATER |
Savings: $1,447 Cost: $150 |
- | - | - | - | - | - | - | - | $1,447 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$1,447 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $28,299 Cost: - |
- | - | - | - | $28,299 | 3,264 | - | - | - | - |
- - kWh |
- - kW-months/year |
$28,299 3,264 MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY |
Savings: $2,565 Cost: - |
- | - | $2,565 | 180 | - | - | - | - | - | - |
- - kWh |
$2,565 180 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $53,356 Cost: $9,099 |
$890 | 29,016 | $3,066 | 248 | $28,299 | 3,264 | $19,654 | 5,328,650 | $1,447 | - | $890 29,016 kWh |
$3,066 248 kW-months/year |
$28,299 3,264 MMBtu |
$19,654 5,328,650 Tgal |
$1,447 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $24,693 Cost: $8,119 |
$688 | 22,861 | $2,904 | 226 | - | - | $19,654 | 5,328,650 | $1,447 | - | $688 22,861 kWh |
$2,904 226 kW-months/year |
- - MMBtu |
$19,654 5,328,650 Tgal |
$1,447 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Ancillary Material Cost |