Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 1999 |
Principal Product | Coated Plastic Parts |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $1,000,000-$5,000,000 |
# of Employees | 102 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 20,000,000 Pieces |
Production Hrs. Annual | 2,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $47,026 | 649,179 | kWh | $0.07 |
Electricity Demand | $59,521 | 5,292 | kW-months/year | $11.25 |
Electricity Fees | $406 | - | $ | - |
Natural Gas | $32,469 | 9,846 | MMBtu | $3.30 |
TOTAL ENERGY COSTS | $139,422 | |||
RECOMMENDED SAVINGS* | $79,066 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $25,733 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,280 Cost: $7,301 |
$1,897 | 32,825 | $2,383 | 165 | - | - | - | - | - | - | - | - |
$1,897 32,825 kWh |
$2,383 165 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $680 Cost: $700 |
- | - | - | - | $680 | 237 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$680 237 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $667 Cost: $300 |
$269 | 4,689 | $398 | 28 | - | - | - | - | - | - | - | - |
$269 4,689 kWh |
$398 28 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $349 Cost: $1,000 |
$134 | 2,345 | $215 | 14 | - | - | - | - | - | - | - | - |
$134 2,345 kWh |
$215 14 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $815 Cost: $990 |
- | - | - | - | $815 | 247 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$815 247 MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $13,503 Cost: $3,700 |
- | - | - | - | - | - | $1,503 | 4,680 | - | - | $12,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,503 4,680 lb |
- - $ |
$12,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.8135 USE LOW VOC OR WATER BASED PAINT |
Savings: $5,439 Cost: $500 |
- | - | - | - | - | - | - | - | - | - | $5,439 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
$5,439 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $53,333 Cost: $1,548 |
- | - | - | - | - | - | - | - | $53,333 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$53,333 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $79,066 Cost: $16,039 |
$2,300 | 39,859 | $2,996 | 207 | $1,495 | 484 | $1,503 | 4,680 | $53,333 | - | $17,439 | - | $2,300 39,859 kWh |
$2,996 207 kW-months/year |
$1,495 484 MMBtu |
$1,503 4,680 lb |
$53,333 - $ |
$17,439 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $25,733 Cost: $14,491 |
$2,300 | 39,859 | $2,996 | 207 | $1,495 | 484 | $1,503 | 4,680 | - | - | $17,439 | - | $2,300 39,859 kWh |
$2,996 207 kW-months/year |
$1,495 484 MMBtu |
$1,503 4,680 lb |
- - $ |
$17,439 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |