Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 1999 |
Principal Product | Plastic Injection Molding |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 25,000 |
Annual Production | 36,000,000 Pieces |
Production Hrs. Annual | 8,400 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $101,237 | 2,466,295 | kWh | $0.04 |
Electricity Demand | $47,253 | 4,140 | kW-months/year | $11.41 |
Electricity Fees | $6,763 | - | $ | - |
Natural Gas | $8,391 | 1,523 | MMBtu | $5.51 |
TOTAL ENERGY COSTS | $163,644 | |||
RECOMMENDED SAVINGS* | $40,263 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (haz) | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (haz) | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,736 Cost: $220 |
$1,935 | 55,393 | $1,801 | 158 | - | - | - | - | - | - |
$1,935 55,393 kWh |
$1,801 158 kW-months/year |
- - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $78 Cost: $200 |
$53 | 1,465 | $25 | 2 | - | - | - | - | - | - |
$53 1,465 kWh |
$25 2 kW-months/year |
- - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,510 Cost: $200 |
$1,655 | 47,479 | $855 | 75 | - | - | - | - | - | - |
$1,655 47,479 kWh |
$855 75 kW-months/year |
- - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $15,807 Cost: $40,000 |
- | - | - | - | $15,807 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$15,807 - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.7131 USE A RAG RECYCLE SERVICE |
Savings: $925 Cost: - |
- | - | - | - | - | - | $925 | 450 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$925 450 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.424 IMPROVE SPACE COMFORT CONDITIONING |
Savings: $6,000 Cost: $3,600 |
- | - | - | - | - | - | - | - | $6,000 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - lb |
$6,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $11,207 Cost: $40,000 |
- | - | - | - | - | - | - | - | $11,207 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - lb |
$11,207 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,263 Cost: $84,220 |
$3,643 | 104,337 | $2,681 | 235 | $15,807 | - | $925 | 450 | $17,207 | - | $3,643 104,337 kWh |
$2,681 235 kW-months/year |
$15,807 - $ |
$925 450 lb |
$17,207 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (haz) | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (haz) | Primary Product |