Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 1999 |
Principal Product | Glass Products |
NAICS | n/a |
SIC | 3231 - Products Of Purchased Glass |
Sales | $10,000,000-$50,000,000 |
# of Employees | 96 |
Plant Area (Sq.Ft.) | 84,000 |
Annual Production | 11,000 Tons |
Production Hrs. Annual | 6,120 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $292,889 | 5,411,196 | kWh | $0.05 |
Electricity Demand | $53,944 | 12,816 | kW-months/year | $4.21 |
Electricity Fees | $42,807 | - | $ | - |
Natural Gas | $15,615 | 2,694 | MMBtu | $5.80 |
TOTAL ENERGY COSTS | $405,255 | |||
RECOMMENDED SAVINGS* | $39,223 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,436 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Water Consumption | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Water Consumption | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,038 Cost: $3,557 |
$2,717 | 45,428 | $1,307 | 110 | - | - | - | - | $100 | - | $914 | - | - | - | - | - |
$2,717 45,428 kWh |
$1,307 110 kW-months/year |
- - MMBtu |
- - lb |
$100 - $ |
$914 - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD |
Savings: $4,796 Cost: $2,000 |
$2,567 | 69,461 | $2,424 | 204 | - | - | - | - | - | - | - | - | $(-195) | - | - | - |
$2,567 69,461 kWh |
$2,424 204 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
$(-195) - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $19,748 Cost: $500 |
$19,748 | 433,470 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$19,748 433,470 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2443 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR |
Savings: $7,215 Cost: $10,000 |
- | - | - | - | $7,215 | 1,244 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$7,215 1,244 MMBtu |
- - lb |
- - $ |
- - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $1,436 Cost: - |
- | - | - | - | - | - | $1,436 | 126,225 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,436 126,225 lb |
- - $ |
- - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $990 Cost: $400 |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | $990 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - Tgal |
$990 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $39,223 Cost: $16,457 |
$25,032 | 548,359 | $3,731 | 314 | $7,215 | 1,244 | $1,436 | 126,225 | $100 | - | $914 | - | $(-195) | - | $990 | - | $25,032 548,359 kWh |
$3,731 314 kW-months/year |
$7,215 1,244 MMBtu |
$1,436 126,225 lb |
$100 - $ |
$914 - $ |
$(-195) - Tgal |
$990 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,436 Cost: - |
- | - | - | - | - | - | $1,436 | 126,225 | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
$1,436 126,225 lb |
- - $ |
- - $ |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Water Consumption | Primary Product | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Water Consumption | Primary Product |