Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 2001 |
Principal Product | Steel Castings |
NAICS | n/a |
SIC | 3325 - Steel Foundries, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 312 |
Plant Area (Sq.Ft.) | 350,000 |
Annual Production | 14,600 Tons |
Production Hrs. Annual | 6,240 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,596,875 | 34,081,478 | kWh | $0.05 |
Electricity Demand | $423,835 | 168,696 | kW-months/year | $2.51 |
Electricity Fees | $(-21,278) | - | $ | - |
Natural Gas | $490,821 | 154,301 | MMBtu | $3.18 |
TOTAL ENERGY COSTS | $2,490,253 | |||
RECOMMENDED SAVINGS* | $162,966 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $81,057 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $5,246 Cost: $11,850 |
$5,246 | 206,331 | - | - | - | - | - | - |
$5,246 206,331 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,577 Cost: $950 |
$3,841 | 139,508 | $2,736 | 192 | - | - | - | - |
$3,841 139,508 kWh |
$2,736 192 kW-months/year |
- - MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $12,663 Cost: $4,200 |
- | - | - | - | $12,663 | 4,078 | - | - |
- - kWh |
- - kW-months/year |
$12,663 4,078 MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $12,480 Cost: $27,000 |
- | - | - | - | $12,480 | 3,925 | - | - |
- - kWh |
- - kW-months/year |
$12,480 3,925 MMBtu |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5244 RECOVER METALS FROM CASTING SAND |
Savings: $64,000 Cost: - |
- | - | - | - | - | - | $64,000 | 3,682,800 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$64,000 3,682,800 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5221 RECYCLE CASTING SAND |
Savings: $48,000 Cost: - |
- | - | - | - | - | - | $48,000 | 16,740,000 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$48,000 16,740,000 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $14,000 Cost: - |
- | - | - | - | - | - | $14,000 | 1,399,680 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$14,000 1,399,680 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $162,966 Cost: $44,000 |
$9,087 | 345,839 | $2,736 | 192 | $25,143 | 8,003 | $126,000 | 21,822,480 | $9,087 345,839 kWh |
$2,736 192 kW-months/year |
$25,143 8,003 MMBtu |
$126,000 21,822,480 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $81,057 Cost: $27,950 |
$3,841 | 139,508 | $2,736 | 192 | $12,480 | 3,925 | $62,000 | 18,139,680 | $3,841 139,508 kWh |
$2,736 192 kW-months/year |
$12,480 3,925 MMBtu |
$62,000 18,139,680 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) |