IAC logo
IAC Assessment: UM0188
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UM0188
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Michigan
Assessment Year 2001
Principal Product Engineered Coatings
NAICS n/a
SIC 2851 - Paints And Allied Products
Sales $5,000,000-$10,000,000
# of Employees 43
Plant Area (Sq.Ft.) 50,000
Annual Production 475 Thousand Gallons
Production Hrs. Annual 2,210
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $17,995 299,912 kWh $0.06
Electricity Demand $26,559 1,908 kW-months/year $13.92
Electricity Fees $1,750 - $ -
Natural Gas $26,333 3,481 MMBtu $7.56
TOTAL ENERGY COSTS $72,637
RECOMMENDED SAVINGS* $18,439 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,333
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,363
Cost:
$1,083
$654 110,461 $709 52 - - - - $654
110,461
kWh
$709
52
kW-months/year
-
-
MMBtu
-
-
$
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$1,080
Cost:
$500
$1,080 17,873 - - - - - - $1,080
17,873
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$12,400
Cost:
$2,800
- - - - $12,400 1,678 - - -
-
kWh
-
-
kW-months/year
$12,400
1,678
MMBtu
-
-
$
04: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$263
Cost:
$1,020
- - - - $263 35 - - -
-
kWh
-
-
kW-months/year
$263
35
MMBtu
-
-
$
05: 4.6310 INSTALL AN UNINTERUPTABLE POWER SUPPLY Savings:
$3,333
Cost:
$1,500
- - - - - - $3,333 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$3,333
-
$
TOTAL RECOMMENDED Savings:
$18,439
Cost:
$6,903
$1,734 128,334 $709 52 $12,663 1,713 $3,333 - $1,734
128,334
kWh
$709
52
kW-months/year
$12,663
1,713
MMBtu
$3,333
-
$
TOTAL IMPLEMENTED Savings:
$3,333
Cost:
$1,500
- - - - - - $3,333 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$3,333
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes