IAC Assessment: UM0301
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UM0301
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Michigan
Assessment Year 2006
Principal Product Electro Deposition Painting / Powder Coating
NAICS 332813 - Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3471 - Plating And Polishing
Sales $10,000,000-$50,000,000
# of Employees 225
Plant Area (Sq.Ft.) 185,000
Annual Production 5,000,000 Pieces
Production Hrs. Annual 4,335
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $10,713 4,817,000 kWh $0.00
Electricity Demand $215,055 10,713 kW-months/year $20.07
Electricity Fees $5,410 - $ -
Natural Gas $1,082,100 100,002 MMBtu $10.82
TOTAL ENERGY COSTS $1,313,278
RECOMMENDED SAVINGS* $47,788 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,536
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.2511 INSULATE BARE EQUIPMENT Savings:
$9,958
Cost:
$30,000
- - - - $9,958 776 -
-
kWh
-
-
kW-months/year
$9,958
776
MMBtu
02: 2.2511 INSULATE BARE EQUIPMENT Savings:
$6,754
Cost:
$1,971
- - - - $6,754 520 -
-
kWh
-
-
kW-months/year
$6,754
520
MMBtu
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$6,429
Cost:
$9,875
- - - - $6,429 495 -
-
kWh
-
-
kW-months/year
$6,429
495
MMBtu
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$6,344
Cost:
$500
- - - - $6,344 458 -
-
kWh
-
-
kW-months/year
$6,344
458
MMBtu
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$7,457
Cost:
$375
$3,567 71,391 $3,890 194 - - $3,567
71,391
kWh
$3,890
194
kW-months/year
-
-
MMBtu
06: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE Savings:
$4,498
Cost:
$738
$3,183 64,104 $1,315 66 - - $3,183
64,104
kWh
$1,315
66
kW-months/year
-
-
MMBtu
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,325
Cost:
-
$1,569 31,602 $1,756 88 - - $1,569
31,602
kWh
$1,756
88
kW-months/year
-
-
MMBtu
08: 2.7141 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS Savings:
$1,415
Cost:
$1,363
$668 13,452 $747 37 - - $668
13,452
kWh
$747
37
kW-months/year
-
-
MMBtu
09: 2.2711 UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING Savings:
$328
Cost:
$328
$(-47) (-949) $(-52) (-3) $427 39 $(-47)
(-949)
kWh
$(-52)
(-3)
kW-months/year
$427
39
MMBtu
10: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,062
Cost:
$300
$506 10,192 $556 28 - - $506
10,192
kWh
$556
28
kW-months/year
-
-
MMBtu
11: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$218
Cost:
$500
- - - - $218 17 -
-
kWh
-
-
kW-months/year
$218
17
MMBtu
TOTAL RECOMMENDED Savings:
$47,788
Cost:
$45,950
$9,446 189,792 $8,212 410 $30,130 2,305 $9,446
189,792
kWh
$8,212
410
kW-months/year
$30,130
2,305
MMBtu
TOTAL IMPLEMENTED Savings:
$17,536
Cost:
$2,346
$5,136 102,993 $5,646 282 $6,754 520 $5,136
102,993
kWh
$5,646
282
kW-months/year
$6,754
520
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas