Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 2011 |
Principal Product | Aluminum slugs |
NAICS | 332119 - Metal Crown, Closure, and Other Metal Stamping (except Automotive) |
SIC | 3466 - Crowns And Closures |
Sales | <$500,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 72,000 |
Annual Production | 86,000,000 Pounds |
Production Hrs. Annual | 7,824 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $332,865 | 5,839,740 | kWh | $0.06 |
Natural Gas | $1,264,839 | 195,593 | MMBtu | $6.47 |
TOTAL ENERGY COSTS | $1,597,704 | |||
RECOMMENDED SAVINGS* | $76,519 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,244 |
#|Description |
Savings Cost |
Status | Natural Gas | Other Gas | Natural Gas | Other Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1116 IMPROVE COMBUSTION CONTROL CAPABILITY |
Savings: $38,198 Cost: $7,100 |
$38,198 | 5,904 | - | - |
$38,198 5,904 MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1116 IMPROVE COMBUSTION CONTROL CAPABILITY |
Savings: $3,190 Cost: $2,000 |
$3,190 | 493 | - | - |
$3,190 493 MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $30,887 Cost: $50,000 |
- | - | $30,887 | 39,981 |
- - MMBtu |
$30,887 39,981 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1135 REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY |
Savings: $4,244 Cost: $1,000 |
$4,244 | 656 | - | - |
$4,244 656 MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $76,519 Cost: $60,100 |
$45,632 | 7,053 | $30,887 | 39,981 | $45,632 7,053 MMBtu |
$30,887 39,981 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,244 Cost: $1,000 |
$4,244 | 656 | - | - | $4,244 656 MMBtu |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Natural Gas | Other Gas | Natural Gas | Other Gas |