Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 2017 |
Principal Product | Aquence Coating and VAA |
NAICS | 335312 - Motor and Generator Manufacturing |
SIC | 3621 - Motors And Generators |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 460,000 |
Annual Production | 1,000,000 Pieces |
Production Hrs. Annual | 5,640 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $467,060 | 4,652,000 | kWh | $0.10 |
Electricity Demand | $111,090 | 10,640 | kW-months/year | $10.44 |
Natural Gas | $265,266 | 55,451 | MMBtu | $4.78 |
TOTAL ENERGY COSTS | $843,416 | |||
RECOMMENDED SAVINGS* | $69,037 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $3,265 Cost: $4,500 |
$3,265 | 32,653 | - | - | - | - | - | - |
$3,265 32,653 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $42,701 Cost: $105,530 |
$30,964 | 309,636 | $6,878 | 659 | - | - | $4,859 | - |
$30,964 309,636 kWh |
$6,878 659 kW-months/year |
- - MMBtu |
$4,859 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2514 COVER OPEN TANKS |
Savings: $23,071 Cost: $2,137 |
- | - | - | - | $23,071 | 4,827 | - | - |
- - kWh |
- - kW-months/year |
$23,071 4,827 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $69,037 Cost: $112,167 |
$34,229 | 342,289 | $6,878 | 659 | $23,071 | 4,827 | $4,859 | - | $34,229 342,289 kWh |
$6,878 659 kW-months/year |
$23,071 4,827 MMBtu |
$4,859 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes |