Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2003 |
Principal Product | frozen dessert |
NAICS | 311520 - Ice Cream and Frozen Dessert Manufacturing |
SIC | 2024 - Ice Cream And Frozen Desserts |
Sales | <$500,000 |
# of Employees | 11 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 3,000,000 Pieces |
Production Hrs. Annual | 2,284 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $3,128 | 113,679 | kWh | $0.03 |
Electricity Demand | $3,917 | 492 | kW-months/year | $7.96 |
TOTAL ENERGY COSTS | $7,045 | |||
RECOMMENDED SAVINGS* | $5,451 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $1 Cost: - |
$1 | - | - | - | - | - |
$1 - kW-months/year |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD |
Savings: $150 Cost: - |
- | - | - | - | $150 | - |
- - kW-months/year |
- - MMBtu |
$150 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $2,957 Cost: - |
$2,957 | 336 | - | - | - | - |
$2,957 336 kW-months/year |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $2,285 Cost: - |
$2,285 | 180 | - | - | - | - |
$2,285 180 kW-months/year |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1231 ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS |
Savings: $1 Cost: - |
$1 | - | - | - | - | - |
$1 - kW-months/year |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $57 Cost: $55 |
- | - | $57 | 14 | - | - |
- - kW-months/year |
$57 14 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $5,451 Cost: $55 |
$5,244 | 516 | $57 | 14 | $150 | - | $5,244 516 kW-months/year |
$57 14 MMBtu |
$150 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kW-months/year |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Demand | Natural Gas | Ancillary Material Cost |