Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2005 |
Principal Product | cheese |
NAICS | 311513 - Cheese Manufacturing |
SIC | 2022 - Cheese, Natural And Processed |
Sales | $10,000,000-$50,000,000 |
# of Employees | 83 |
Plant Area (Sq.Ft.) | 32,300 |
Annual Production | 94,000,000 Pounds |
Production Hrs. Annual | 3,120 |
Location (State) | ID |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $338,156 | 12,284,555 | kWh | $0.03 |
Electricity Demand | $58,652 | 21,107 | kW-months/year | $2.78 |
Natural Gas | $58,864 | 98,218 | MMBtu | $0.60 |
TOTAL ENERGY COSTS | $455,672 | |||
RECOMMENDED SAVINGS* | $293,110 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $6,140 Cost: $18,959 |
$4,110 | 149,200 | $2,030 | 574 | - | - |
$4,110 149,200 kWh |
$2,030 574 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $840 Cost: $360 |
$560 | 20,360 | $280 | 78 | - | - |
$560 20,360 kWh |
$280 78 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,120 Cost: $710 |
$750 | 27,230 | $370 | 105 | - | - |
$750 27,230 kWh |
$370 105 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE |
Savings: $130 Cost: - |
- | - | - | - | $130 | 210 |
- - kWh |
- - kW-months/year |
$130 210 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $340 Cost: $1,380 |
$340 | 12,480 | - | - | - | - |
$340 12,480 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $284,540 Cost: $3,000,000 |
$289,520 | 10,500,000 | $63,810 | 18,000 | $(-68,790) | (-111,614) |
$289,520 10,500,000 kWh |
$63,810 18,000 kW-months/year |
$(-68,790) (-111,614) MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $293,110 Cost: $3,021,409 |
$295,280 | 10,709,270 | $66,490 | 18,757 | $(-68,660) | (-111,404) | $295,280 10,709,270 kWh |
$66,490 18,757 kW-months/year |
$(-68,660) (-111,404) MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |