Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2005 |
Principal Product | Pipe |
NAICS | 331210 - Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
SIC | 3317 - Steel Pipe And Tubes |
Sales | $5,000,000-$10,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 75,900 |
Annual Production | 8,000 Tons |
Production Hrs. Annual | 2,350 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $31,590 | 1,138,905 | kWh | $0.03 |
Electricity Demand | $55,623 | 6,159 | kW-months/year | $9.03 |
Natural Gas | $132,072 | 21,053 | MMBtu | $6.27 |
TOTAL ENERGY COSTS | $219,285 | |||
RECOMMENDED SAVINGS* | $102,630 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.511 EXPAND OPERATIONS INTO UNUSED SPACE |
Savings: $84,030 Cost: $200,000 |
- | - | - | - | $84,030 | 13,338 |
- - kWh |
- - kW-months/year |
$84,030 13,338 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $9,270 Cost: - |
- | - | $9,270 | 781 | - | - |
- - kWh |
$9,270 781 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,180 Cost: $3,040 |
$1,790 | 64,080 | $4,390 | 370 | - | - |
$1,790 64,080 kWh |
$4,390 370 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,680 Cost: $240 |
$840 | 30,170 | $1,840 | 155 | - | - |
$840 30,170 kWh |
$1,840 155 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $470 Cost: $2,900 |
- | - | $470 | 40 | - | - |
- - kWh |
$470 40 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $102,630 Cost: $206,180 |
$2,630 | 94,250 | $15,970 | 1,346 | $84,030 | 13,338 | $2,630 94,250 kWh |
$15,970 1,346 kW-months/year |
$84,030 13,338 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |