IAC Assessment: UU0135
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UU0135
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Utah
Assessment Year 2018
Principal Product Commercial Wood Products
NAICS 321999 - All Other Miscellaneous Wood Product Manufacturing
SIC 2499 - Wood Products, Nec
Sales $5,000,000-$10,000,000
# of Employees 40
Plant Area (Sq.Ft.) 80,000
Annual Production 1,500 Units
Production Hrs. Annual 2,184
Location (State) UT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $44,696 469,190 kWh $0.10
Electricity Fees $22,468 - $ -
Natural Gas $39,971 4,935 MMBtu $8.10
TOTAL ENERGY COSTS $107,135
RECOMMENDED SAVINGS* $20,537 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $5,919
#|Description Savings
Cost
Status Electricity Usage Electricity Fees Natural Gas Electricity Usage Electricity Fees Natural Gas
$ kWh $ $ $ MMBtu
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER Savings:
$10,541
Cost:
$800
- - $10,541 - - - -
-
kWh
$10,541
-
$
-
-
MMBtu
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$4,170
Cost:
$993
$3,112 32,542 $1,058 - - - $3,112
32,542
kWh
$1,058
-
$
-
-
MMBtu
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,077
Cost:
$1,970
$3,042 31,930 $1,035 - - - $3,042
31,930
kWh
$1,035
-
$
-
-
MMBtu
04: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS Savings:
$1,749
Cost:
$900
$709 7,461 $247 - $793 99 $709
7,461
kWh
$247
-
$
$793
99
MMBtu
TOTAL RECOMMENDED Savings:
$20,537
Cost:
$4,663
$6,862 71,933 $12,881 - $793 99 $6,862
71,933
kWh
$12,881
-
$
$793
99
MMBtu
TOTAL IMPLEMENTED Savings:
$5,919
Cost:
$1,893
$3,820 40,003 $1,305 - $793 99 $3,820
40,003
kWh
$1,305
-
$
$793
99
MMBtu
Savings
Cost
$ kWh $ $ $ MMBtu
Electricity Usage Electricity Fees Natural Gas Electricity Usage Electricity Fees Natural Gas