Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2019 |
Principal Product | Architectural Woodwork |
NAICS | 337212 - Custom Architectural Woodwork and Millwork Manufacturing |
SIC | 2435 - Hardwood Veneer And Plywood |
Sales | $50,000,000-$100,000,000 |
# of Employees | 196 |
Plant Area (Sq.Ft.) | 130,000 |
Annual Production | 50,000,000 Units |
Production Hrs. Annual | 4,800 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $100,212 | 2,737,800 | kWh | $0.04 |
Electricity Demand | $160,944 | 9,764 | kW-months/year | $16.48 |
Electricity Fees | $45,379 | - | $ | - |
Natural Gas | $17,229 | 13,833 | MMBtu | $1.25 |
TOTAL ENERGY COSTS | $352,883 | |||
RECOMMENDED SAVINGS* | $17,126 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,082 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,712 Cost: $2,024 |
$1,410 | 38,532 | $1,301 | 79 | - | - |
$1,410 38,532 kWh |
$1,301 79 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,961 Cost: $2,600 |
$922 | 25,200 | $1,038 | 63 | - | - |
$922 25,200 kWh |
$1,038 63 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $4,768 Cost: $12,634 |
$4,132 | 112,896 | $636 | 39 | - | - |
$4,132 112,896 kWh |
$636 39 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,497 Cost: $2,300 |
$867 | 23,682 | $1,630 | 99 | - | - |
$867 23,682 kWh |
$1,630 99 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3134 SHIFT FROM DAYTIME TO NIGHTTIME OPERATION |
Savings: $1,315 Cost: $2,600 |
- | - | $1,315 | 80 | - | - |
- - kWh |
$1,315 80 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,874 Cost: $3,125 |
- | - | - | - | $3,874 | 3,099 |
- - kWh |
- - kW-months/year |
$3,874 3,099 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $17,126 Cost: $25,283 |
$7,331 | 200,310 | $5,920 | 359 | $3,874 | 3,099 | $7,331 200,310 kWh |
$5,920 359 kW-months/year |
$3,874 3,099 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,082 Cost: $7,449 |
$2,277 | 62,214 | $2,931 | 178 | $3,874 | 3,099 | $2,277 62,214 kWh |
$2,931 178 kW-months/year |
$3,874 3,099 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |