Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2020 |
Principal Product | Water Distribution |
NAICS | 221310 - Water Supply and Irrigation Systems |
SIC | 4941 - Water Supply |
Sales | $5,000,000-$10,000,000 |
# of Employees | 10 |
Plant Area (Sq.Ft.) | 13,500 |
Annual Production | 7,500,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $169,807 | 5,054,406 | kWh | $0.03 |
Electricity Demand | $74,608 | 10,752 | kW-months/year | $6.94 |
Electricity Fees | $38,546 | - | $ | - |
TOTAL ENERGY COSTS | $282,961 | |||
RECOMMENDED SAVINGS* | $69,244 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $44,792 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $39,976 Cost: $124,680 |
$31,140 | 929,551 | $8,836 | 1,273 |
$31,140 929,551 kWh |
$8,836 1,273 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3322 USE EXISTING DAM TO GENERATE ELECTRICITY |
Savings: $24,451 Cost: $120,000 |
$13,210 | 394,445 | $11,241 | 1,620 |
$13,210 394,445 kWh |
$11,241 1,620 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2211 USE OPTIMUM TEMPERATURE |
Savings: $4,303 Cost: - |
$3,341 | 99,734 | $961 | 139 |
$3,341 99,734 kWh |
$961 139 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $514 Cost: $2,100 |
$406 | 12,100 | $108 | 16 |
$406 12,100 kWh |
$108 16 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $69,244 Cost: $246,780 |
$48,097 | 1,435,830 | $21,147 | 3,047 | $48,097 1,435,830 kWh |
$21,147 3,047 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $44,792 Cost: $126,780 |
$34,887 | 1,041,385 | $9,905 | 1,427 | $34,887 1,041,385 kWh |
$9,905 1,427 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |