IAC Assessment: UU0195
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UU0195
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Utah
Assessment Year 2022
Principal Product Animal Feed
NAICS 311119 - Other Animal Food Manufacturing
SIC 2048 - Prepared Feeds, Nec
Sales $10,000,000-$50,000,000
# of Employees 35
Plant Area (Sq.Ft.) 55,000
Annual Production 113,419 Tons
Production Hrs. Annual 5,800
Location (State) UT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $123,065 1,890,113 kWh $0.07
Electricity Demand $48,422 5,124 kW-months/year $9.45
Electricity Fees $22,219 - $ -
Natural Gas $145,456 25,439 MMBtu $5.72
TOTAL ENERGY COSTS $339,162
RECOMMENDED SAVINGS* $46,440 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas
$ kWh $ kW-months/year $ $ $ MMBtu
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER Savings:
$13,680
Cost:
$22,600
- - - - $13,680 - - - -
-
kWh
-
-
kW-months/year
$13,680
-
$
-
-
MMBtu
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$11,177
Cost:
$25,216
- - - - - - $11,177 1,954 -
-
kWh
-
-
kW-months/year
-
-
$
$11,177
1,954
MMBtu
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$5,645
Cost:
$2,000
- - - - $5,645 - - - -
-
kWh
-
-
kW-months/year
$5,645
-
$
-
-
MMBtu
04: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$4,698
Cost:
$20,000
- - - - $4,698 - - - -
-
kWh
-
-
kW-months/year
$4,698
-
$
-
-
MMBtu
05: 2.2511 INSULATE BARE EQUIPMENT Savings:
$3,620
Cost:
$7,340
- - - - - - $3,620 633 -
-
kWh
-
-
kW-months/year
-
-
$
$3,620
633
MMBtu
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,050
Cost:
$218
$2,544 39,070 $506 54 - - - - $2,544
39,070
kWh
$506
54
kW-months/year
-
-
$
-
-
MMBtu
07: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,910
Cost:
$3,500
$1,910 29,330 - - - - - - $1,910
29,330
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,777
Cost:
$3,908
$1,369 21,031 $408 43 - - - - $1,369
21,031
kWh
$408
43
kW-months/year
-
-
$
-
-
MMBtu
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$883
Cost:
$1,000
$713 10,950 $170 18 - - - - $713
10,950
kWh
$170
18
kW-months/year
-
-
$
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$46,440
Cost:
$85,782
$6,536 100,381 $1,084 115 $24,023 - $14,797 2,587 $6,536
100,381
kWh
$1,084
115
kW-months/year
$24,023
-
$
$14,797
2,587
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas