IAC Assessment: UU0198
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UU0198
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Utah
Assessment Year 2022
Principal Product Health Care
NAICS 622110 - General Medical and Surgical Hospitals
SIC 8062 - General Medical & Surgical Hospitals
Sales $10,000,000-$50,000,000
# of Employees 145
Plant Area (Sq.Ft.) 44,353
Annual Production 456 Units
Production Hrs. Annual 8,760
Location (State) UT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $82,539 1,153,761 kWh $0.07
Electricity Demand $20,589 2,634 kW-months/year $7.82
Electricity Fees $10,791 - $ -
Natural Gas $47,136 5,650 MMBtu $8.34
TOTAL ENERGY COSTS $161,055
RECOMMENDED SAVINGS* $31,008 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $31,008
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE Savings:
$13,222
Cost:
$12,000
$5,348 74,822 - - $7,874 944 $5,348
74,822
kWh
-
-
kW-months/year
$7,874
944
MMBtu
02: 2.1224 REPLACE BOILER Savings:
$7,758
Cost:
$4,499
- - - - $7,758 930 -
-
kWh
-
-
kW-months/year
$7,758
930
MMBtu
03: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE Savings:
$5,828
Cost:
$12,000
$5,828 81,515 - - - - $5,828
81,515
kWh
-
-
kW-months/year
-
-
MMBtu
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,182
Cost:
$17,630
$2,713 37,949 $469 60 - - $2,713
37,949
kWh
$469
60
kW-months/year
-
-
MMBtu
05: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$1,018
Cost:
$4,500
$75 1,043 - - $943 113 $75
1,043
kWh
-
-
kW-months/year
$943
113
MMBtu
TOTAL RECOMMENDED Savings:
$31,008
Cost:
$50,629
$13,964 195,329 $469 60 $16,575 1,987 $13,964
195,329
kWh
$469
60
kW-months/year
$16,575
1,987
MMBtu
TOTAL IMPLEMENTED Savings:
$31,008
Cost:
$50,629
$13,964 195,329 $469 60 $16,575 1,987 $13,964
195,329
kWh
$469
60
kW-months/year
$16,575
1,987
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas