Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2022 |
Principal Product | Water Distribution |
NAICS | 221310 - Water Supply and Irrigation Systems |
SIC | 4941 - Water Supply |
Sales | $1,000,000-$5,000,000 |
# of Employees | 9 |
Plant Area (Sq.Ft.) | 16,574 |
Annual Production | 1,002,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $188,878 | 2,314,254 | kWh | $0.08 |
Electricity Demand | $1,622 | 330 | kW-months/year | $4.92 |
Electricity Fees | $190,501 | - | $ | - |
Natural Gas | $7,690 | 893 | MMBtu | $8.62 |
TOTAL ENERGY COSTS | $388,691 | |||
RECOMMENDED SAVINGS* | $55,928 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Water Usage | Electricity Usage | Natural Gas | Water Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $33,490 Cost: $103,200 |
$17,673 | 205,510 | - | - | $15,817 | 5,000 |
$17,673 205,510 kWh |
- - MMBtu |
$15,817 5,000 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $19,358 Cost: $60,000 |
$19,358 | 229,695 | - | - | - | - |
$19,358 229,695 kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $3,080 Cost: $10,070 |
$2,402 | 29,340 | $678 | 70 | - | - |
$2,402 29,340 kWh |
$678 70 MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $55,928 Cost: $173,270 |
$39,433 | 464,545 | $678 | 70 | $15,817 | 5,000 | $39,433 464,545 kWh |
$678 70 MMBtu |
$15,817 5,000 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - MMBtu |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Water Usage | Electricity Usage | Natural Gas | Water Usage |