IAC Assessment: UU0275
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UU0275
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Utah
Assessment Year 2025
Principal Product Machine Parts and Fabricated Metals
NAICS 332710 - Machine Shops
SIC 3599 - Industrial Machinery, Nec
Sales $50,000,000-$100,000,000
# of Employees 210
Plant Area (Sq.Ft.) 95,000
Annual Production 250,000 Units
Production Hrs. Annual 5,800
Location (State) UT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $143,642 3,981,499 kWh $0.04
Electricity Demand $134,673 8,259 kW-months/year $16.31
Electricity Fees $91,067 - $ -
Natural Gas $5,462 592 MMBtu $9.23
Fuel Oil #1 $5,580 211 MMBtu $26.40
TOTAL ENERGY COSTS $380,424
RECOMMENDED SAVINGS* $59,639 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Fuel Oil #1 Electricity Usage Electricity Demand Electricity Fees Fuel Oil #1
$ kWh $ kW-months/year $ $ $ MMBtu
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$5,030
Cost:
$15,960
- - $5,030 245 - - - - -
-
kWh
$5,030
245
kW-months/year
-
-
$
-
-
MMBtu
02: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$33,900
Cost:
$8,025
- - - - $33,900 - - - -
-
kWh
-
-
kW-months/year
$33,900
-
$
-
-
MMBtu
03: 3.1194 USE AUTOMATIC FLOW CONTROL Savings:
$1,516
Cost:
$5,258
$811 22,540 $704 43 - - - - $811
22,540
kWh
$704
43
kW-months/year
-
-
$
-
-
MMBtu
04: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$2,066
Cost:
$2,066
$1,391 38,640 $675 41 - - - - $1,391
38,640
kWh
$675
41
kW-months/year
-
-
$
-
-
MMBtu
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$12,307
Cost:
$10,880
$11,384 316,220 $923 57 - - - - $11,384
316,220
kWh
$923
57
kW-months/year
-
-
$
-
-
MMBtu
06: 2.8226 INCREASE EFFICIENCY OF TRUCKS Savings:
$4,820
Cost:
$8,740
$(-560) (-15,650) - - - - $5,380 211 $(-560)
(-15,650)
kWh
-
-
kW-months/year
-
-
$
$5,380
211
MMBtu
TOTAL RECOMMENDED Savings:
$59,639
Cost:
$50,929
$13,026 361,750 $7,332 386 $33,900 - $5,380 211 $13,026
361,750
kWh
$7,332
386
kW-months/year
$33,900
-
$
$5,380
211
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Fuel Oil #1 Electricity Usage Electricity Demand Electricity Fees Fuel Oil #1