Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Washington |
---|---|
Assessment Year | 2007 |
Principal Product | Tempered glass panes and insulated glass panes |
NAICS | 327215 - Glass Product Manufacturing Made of Purchased Glass |
SIC | 3231 - Products Of Purchased Glass |
Sales | $10,000,000-$50,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 64,000 |
Annual Production | 800,000 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $275,656 | 8,142,000 | kWh | $0.03 |
Electricity Demand | $121,971 | 20,569 | kW-months/year | $5.93 |
Electricity Fees | $10,893 | - | $ | - |
Other Gas | $5,000 | 1,000 | MMBtu | $5.00 |
TOTAL ENERGY COSTS | $468,294 | |||
RECOMMENDED SAVINGS* | $47,913 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,851 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Gas | Administrative Changes | Electricity Usage | Electricity Demand | Other Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $21,263 Cost: $85,000 |
$21,263 | 628,054 | - | - | - | - | - | - |
$21,263 628,054 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $10,893 Cost: $16,323 |
- | - | $10,893 | 1,837 | - | - | - | - |
- - kWh |
$10,893 1,837 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $8,000 Cost: $9,385 |
- | - | - | - | $5,000 | 1,000 | $3,000 | - |
- - kWh |
- - kW-months/year |
$5,000 1,000 MMBtu |
$3,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $5,998 Cost: $2,692 |
$5,998 | 177,158 | - | - | - | - | - | - |
$5,998 177,158 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $700 Cost: $252 |
$820 | 24,216 | - | - | - | - | $(-120) | - |
$820 24,216 kWh |
- - kW-months/year |
- - MMBtu |
$(-120) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $906 Cost: $653 |
$633 | 18,705 | $273 | 46 | - | - | - | - |
$633 18,705 kWh |
$273 46 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $153 Cost: $200 |
$153 | 4,524 | - | - | - | - | - | - |
$153 4,524 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $47,913 Cost: $114,505 |
$28,867 | 852,657 | $11,166 | 1,883 | $5,000 | 1,000 | $2,880 | - | $28,867 852,657 kWh |
$11,166 1,883 kW-months/year |
$5,000 1,000 MMBtu |
$2,880 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,851 Cost: $12,529 |
$6,971 | 205,898 | - | - | $5,000 | 1,000 | $2,880 | - | $6,971 205,898 kWh |
- - kW-months/year |
$5,000 1,000 MMBtu |
$2,880 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Gas | Administrative Changes | Electricity Usage | Electricity Demand | Other Gas | Administrative Changes |