Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Washington |
---|---|
Assessment Year | 2022 |
Principal Product | Aircraft Manufacturing |
NAICS | 336411 - Aircraft Manufacturing |
SIC | 3728 - Aircraft Parts And Equipment, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 600 |
Plant Area (Sq.Ft.) | 94,280 |
Annual Production | 1,000 Units |
Production Hrs. Annual | 8,760 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $137,819 | 1,588,018 | kWh | $0.09 |
Electricity Demand | $1,895 | 535 | kW-months/year | $3.54 |
Electricity Fees | $10,199 | - | $ | - |
Natural Gas | $11,014 | 1,048 | MMBtu | $10.51 |
TOTAL ENERGY COSTS | $160,927 | |||
RECOMMENDED SAVINGS* | $110,660 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,594 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,980 Cost: $800 |
$1,723 | 19,850 | $257 | 73 |
$1,723 19,850 kWh |
$257 73 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,653 Cost: $33,398 |
$9,563 | 110,183 | $2,090 | 590 |
$9,563 110,183 kWh |
$2,090 590 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,961 Cost: $1,423 |
$2,577 | 29,696 | $384 | 109 |
$2,577 29,696 kWh |
$384 109 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $94,066 Cost: $513,443 |
$89,089 | 1,026,366 | $4,977 | 1,406 |
$89,089 1,026,366 kWh |
$4,977 1,406 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $110,660 Cost: $549,064 |
$102,952 | 1,186,095 | $7,708 | 2,178 | $102,952 1,186,095 kWh |
$7,708 2,178 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,594 Cost: $35,621 |
$13,863 | 159,729 | $2,731 | 772 | $13,863 159,729 kWh |
$2,731 772 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |