Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Washington |
---|---|
Assessment Year | 2024 |
Principal Product | Slude, Wastewater |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | $1,000,000-$5,000,000 |
# of Employees | 4 |
Plant Area (Sq.Ft.) | 210,000 |
Annual Production | 40,150 Thousand Gallons |
Production Hrs. Annual | 3,822 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $75,968 | 2,770,827 | kWh | $0.03 |
Electricity Demand | $40,056 | 5,932 | kW-months/year | $6.75 |
Electricity Fees | $10,366 | - | $ | - |
Fuel Oil #1 | $10,300 | 290 | MMBtu | $35.52 |
TOTAL ENERGY COSTS | $136,690 | |||
RECOMMENDED SAVINGS* | $70,945 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #1 | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Fuel Oil #1 | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.114 ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS |
Savings: $8,896 Cost: $25,250 |
- | - | - | - | $8,896 | 230 | - | - |
- - kWh |
- - kW-months/year |
$8,896 230 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.663 LEVEL TWO – INSTALL CONTROL SYSTEM USING IIOT DEVICES WITH COMMUNICATION CAPABILITIES TO STORE DATA TO THE CLOUD |
Savings: $25,793 Cost: $13,368 |
$15,194 | 554,165 | - | - | - | - | $10,599 | - |
$15,194 554,165 kWh |
- - kW-months/year |
- - MMBtu |
$10,599 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.661 LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT |
Savings: $20,435 Cost: $58,800 |
$19,868 | 735,840 | $567 | 84 | - | - | - | - |
$19,868 735,840 kWh |
$567 84 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $12,186 Cost: $5,713 |
$12,186 | 444,738 | - | - | - | - | - | - |
$12,186 444,738 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $53 Cost: $229 |
$53 | 1,971 | - | - | - | - | - | - |
$53 1,971 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $3,582 Cost: $7,250 |
$3,582 | 130,645 | - | - | - | - | - | - |
$3,582 130,645 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $70,945 Cost: $110,610 |
$50,883 | 1,867,359 | $567 | 84 | $8,896 | 230 | $10,599 | - | $50,883 1,867,359 kWh |
$567 84 kW-months/year |
$8,896 230 MMBtu |
$10,599 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #1 | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Fuel Oil #1 | One-time Revenue or Avoided Cost |