Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1997 |
Principal Product | Gears |
NAICS | n/a |
SIC | 3398 - Metal Heat Treating |
Sales | $10,000,000-$50,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 200,000 |
Annual Production | 250,000 Pieces |
Production Hrs. Annual | 6,800 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $168,201 | 7,162,661 | kWh | $0.02 |
Electricity Demand | $121,427 | 16,886 | kW-months/year | $7.19 |
Electricity Fees | $5,637 | - | $ | - |
Natural Gas | $364,766 | 111,787 | MMBtu | $3.26 |
TOTAL ENERGY COSTS | $740,417 | |||
RECOMMENDED SAVINGS* | $227,875 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $5,254 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $29,800 Cost: - |
- | - | - | - | - | - | - | - | $29,800 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
$29,800 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.4151 MINIMIZE WATER USAGE |
Savings: $4,920 Cost: - |
- | - | - | - | $4,920 | 3,672,000 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,920 3,672,000 Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.1161 ELIMINATE/REDUCE AN OPERATION |
Savings: $2,227 Cost: - |
- | - | - | - | - | - | $(-3,898) | - | - | - | $6,125 | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$(-3,898) - $ |
- - $ |
$6,125 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.7137 REPLACE CLOTH RAGS WITH PAPER TOWELS |
Savings: $1,450 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $1,450 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
$1,450 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,027 Cost: $480 |
$2,125 | 86,166 | $902 | 114 | - | - | - | - | - | - | - | - | - | - |
$2,125 86,166 kWh |
$902 114 kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $623 Cost: $1,000 |
$422 | 16,999 | $201 | 25 | - | - | - | - | - | - | - | - | - | - |
$422 16,999 kWh |
$201 25 kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $557 Cost: - |
$557 | 22,567 | - | 359 | - | - | - | - | - | - | - | - | - | - |
$557 22,567 kWh |
- 359 kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $271 Cost: $675 |
$271 | 11,137 | - | - | - | - | - | - | - | - | - | - | - | - |
$271 11,137 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.425 ELIMINATE/REDUCE REDUNDANT INSPECTIONS |
Savings: $185,000 Cost: $137,500 |
- | - | - | - | - | - | $185,000 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$185,000 - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $227,875 Cost: $139,655 |
$3,375 | 136,869 | $1,103 | 498 | $4,920 | 3,672,000 | $181,102 | - | $29,800 | - | $6,125 | - | $1,450 | - | $3,375 136,869 kWh |
$1,103 498 kW-months/year |
$4,920 3,672,000 Tgal |
$181,102 - $ |
$29,800 - $ |
$6,125 - $ |
$1,450 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $5,254 Cost: $480 |
$2,125 | 86,166 | $902 | 114 | - | - | $(-3,898) | - | - | - | $6,125 | - | - | - | $2,125 86,166 kWh |
$902 114 kW-months/year |
- - Tgal |
$(-3,898) - $ |
- - $ |
$6,125 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Water Disposal | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost |