Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2012 |
Principal Product | Motor vehicle component |
NAICS | 332618 - Other Fabricated Wire Product Manufacturing |
SIC | 3496 - Misc. Fabricated Wire Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 131 |
Plant Area (Sq.Ft.) | 103,900 |
Annual Production | 5,800,000 Pounds |
Production Hrs. Annual | 8,520 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $249,393 | 3,871,600 | kWh | $0.06 |
Electricity Demand | $88,152 | 7,764 | kW-months/year | $11.35 |
Natural Gas | $19,945 | 2,316 | MMBtu | $8.61 |
TOTAL ENERGY COSTS | $357,490 | |||
RECOMMENDED SAVINGS* | $60,759 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $28,384 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | By-product Production | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $444 Cost: - |
$386 | 5,982 | $59 | 5 | - | - | - | - | - | - | - | - |
$386 5,982 kWh |
$59 5 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,581 Cost: $488 |
$2,888 | 43,500 | $693 | 61 | - | - | - | - | - | - | - | - |
$2,888 43,500 kWh |
$693 61 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $8,926 Cost: - |
$7,155 | 111,101 | $1,771 | 156 | - | - | - | - | - | - | - | - |
$7,155 111,101 kWh |
$1,771 156 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $22,037 Cost: - |
$21,617 | 335,676 | $420 | 37 | - | - | - | - | - | - | - | - |
$21,617 335,676 kWh |
$420 37 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6127 MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT |
Savings: $1,994 Cost: $191 |
- | - | - | - | - | - | $1,994 | 232 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,994 232 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $772 Cost: - |
$772 | 11,871 | - | - | - | - | - | - | - | - | - | - |
$772 11,871 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $341 Cost: - |
- | - | - | - | $341 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$341 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $15,810 Cost: - |
- | - | - | - | - | - | - | - | $15,810 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$15,810 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.424 IMPROVE SPACE COMFORT CONDITIONING |
Savings: $6,854 Cost: $884 |
- | - | - | - | - | - | - | - | - | - | $6,854 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
$6,854 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $60,759 Cost: $1,563 |
$32,818 | 508,130 | $2,943 | 259 | $341 | - | $1,994 | 232 | $15,810 | - | $6,854 | - | $32,818 508,130 kWh |
$2,943 259 kW-months/year |
$341 - $ |
$1,994 232 MMBtu |
$15,810 - $ |
$6,854 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $28,384 Cost: $679 |
$25,277 | 391,047 | $1,113 | 98 | - | - | $1,994 | 232 | - | - | - | - | $25,277 391,047 kWh |
$1,113 98 kW-months/year |
- - $ |
$1,994 232 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | By-product Production | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | By-product Production |