Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2014 |
Principal Product | Formed wire components |
NAICS | 332618 - Other Fabricated Wire Product Manufacturing |
SIC | 3496 - Misc. Fabricated Wire Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 95 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 7,000,000 Pounds |
Production Hrs. Annual | 4,160 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $80,968 | 1,227,120 | kWh | $0.07 |
Electricity Demand | $26,156 | 3,487 | kW-months/year | $7.50 |
Electricity Fees | $7,754 | - | $ | - |
TOTAL ENERGY COSTS | $114,878 | |||
RECOMMENDED SAVINGS* | $26,242 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $21,703 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $13,399 Cost: $38,020 |
$6,873 | 104,139 | $4,235 | 565 | - | - | $2,291 | - |
$6,873 104,139 kWh |
$4,235 565 kW-months/year |
- - $ |
$2,291 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $2,588 Cost: - |
$1,949 | 29,536 | $639 | 85 | - | - | - | - |
$1,949 29,536 kWh |
$639 85 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,070 Cost: $400 |
$3,818 | 57,842 | $1,252 | 167 | - | - | - | - |
$3,818 57,842 kWh |
$1,252 167 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,039 Cost: $4,600 |
$2,334 | 35,345 | $705 | 94 | - | - | - | - |
$2,334 35,345 kWh |
$705 94 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $680 Cost: $127 |
$512 | 7,765 | $168 | 22 | - | - | - | - |
$512 7,765 kWh |
$168 22 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $211 Cost: - |
- | - | - | - | $211 | - | - | - |
- - kWh |
- - kW-months/year |
$211 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $820 Cost: $400 |
$530 | 8,037 | $290 | 39 | - | - | - | - |
$530 8,037 kWh |
$290 39 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $435 Cost: $1,138 |
$260 | 4,885 | - | - | - | - | $175 | - |
$260 4,885 kWh |
- - kW-months/year |
- - $ |
$175 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $26,242 Cost: $44,685 |
$16,276 | 247,549 | $7,289 | 972 | $211 | - | $2,466 | - | $16,276 247,549 kWh |
$7,289 972 kW-months/year |
$211 - $ |
$2,466 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $21,703 Cost: $39,558 |
$12,900 | 196,402 | $6,126 | 817 | $211 | - | $2,466 | - | $12,900 196,402 kWh |
$6,126 817 kW-months/year |
$211 - $ |
$2,466 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Ancillary Material Cost |