Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2015 |
Principal Product | Stone veneer |
NAICS | 212311 - Dimension Stone Mining and Quarrying |
SIC | 1411 - Dimension Stone |
Sales | $10,000,000-$50,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 65,000 |
Annual Production | 110,000 Tons |
Production Hrs. Annual | 4,590 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $153,043 | 2,283,535 | kWh | $0.07 |
Electricity Demand | $55,065 | 5,953 | kW-months/year | $9.25 |
LPG | $100,170 | 10,642 | MMBtu | $9.41 |
TOTAL ENERGY COSTS | $308,278 | |||
RECOMMENDED SAVINGS* | $17,368 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,380 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | LPG | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | LPG | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $9,713 Cost: $20,000 |
$7,137 | 106,529 | $2,576 | 279 | - | - | - | - |
$7,137 106,529 kWh |
$2,576 279 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,865 Cost: $3,846 |
$1,981 | 29,564 | $677 | 73 | - | - | $207 | - |
$1,981 29,564 kWh |
$677 73 kW-months/year |
- - MMBtu |
$207 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,288 Cost: $6,900 |
$1,893 | 45,384 | - | - | - | - | $395 | - |
$1,893 45,384 kWh |
- - kW-months/year |
- - MMBtu |
$395 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,227 Cost: $575 |
$1,227 | 18,309 | - | - | - | - | - | - |
$1,227 18,309 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,054 Cost: $1,390 |
- | - | - | - | $1,054 | 112 | - | - |
- - kWh |
- - kW-months/year |
$1,054 112 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $221 Cost: $476 |
$221 | 3,299 | - | - | - | - | - | - |
$221 3,299 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $17,368 Cost: $33,187 |
$12,459 | 203,085 | $3,253 | 352 | $1,054 | 112 | $602 | - | $12,459 203,085 kWh |
$3,253 352 kW-months/year |
$1,054 112 MMBtu |
$602 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,380 Cost: $11,321 |
$5,101 | 93,257 | $677 | 73 | - | - | $602 | - | $5,101 93,257 kWh |
$677 73 kW-months/year |
- - MMBtu |
$602 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | LPG | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | LPG | One-time Revenue or Avoided Cost |