Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2016 |
Principal Product | Plastic pallets |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 2,100,000 Pieces |
Production Hrs. Annual | 8,568 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,831,439 | 36,133,292 | kWh | $0.05 |
Electricity Demand | $817,049 | 187,583 | kW-months/year | $4.36 |
Electricity Fees | $64,977 | - | $ | - |
Natural Gas | $32,585 | 4,785 | MMBtu | $6.81 |
TOTAL ENERGY COSTS | $2,746,050 | |||
RECOMMENDED SAVINGS* | $64,869 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $29,023 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $15,282 Cost: $26,000 |
$13,640 | 269,092 | $1,642 | 377 |
$13,640 269,092 kWh |
$1,642 377 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $21,220 Cost: $23,066 |
$18,940 | 373,644 | $2,280 | 523 |
$18,940 373,644 kWh |
$2,280 523 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,011 Cost: $3,340 |
$3,011 | 59,406 | - | - |
$3,011 59,406 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $5,195 Cost: $825 |
$4,790 | 94,498 | $405 | 93 |
$4,790 94,498 kWh |
$405 93 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,792 Cost: $280 |
$4,278 | 84,386 | $514 | 118 |
$4,278 84,386 kWh |
$514 118 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4234 COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER |
Savings: $5,896 Cost: $2,068 |
$5,263 | 103,812 | $633 | 145 |
$5,263 103,812 kWh |
$633 145 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $7,050 Cost: $1,650 |
$6,292 | 124,132 | $758 | 174 |
$6,292 124,132 kWh |
$758 174 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $2,423 Cost: $9,400 |
$2,033 | 40,105 | $390 | 90 |
$2,033 40,105 kWh |
$390 90 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $64,869 Cost: $66,629 |
$58,247 | 1,149,075 | $6,622 | 1,520 | $58,247 1,149,075 kWh |
$6,622 1,520 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $29,023 Cost: $26,686 |
$26,229 | 517,436 | $2,794 | 641 | $26,229 517,436 kWh |
$2,794 641 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |