Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2019 |
Principal Product | Precision Machined Parts |
NAICS | 332710 - Machine Shops |
SIC | 3499 - Fabricated Metal Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 131 |
Plant Area (Sq.Ft.) | 90,000 |
Annual Production | 1,000,000 Units |
Production Hrs. Annual | 7,200 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $285,187 | 4,672,365 | kWh | $0.06 |
Electricity Demand | $111,626 | 8,256 | kW-months/year | $13.52 |
Electricity Fees | $11,404 | - | $ | - |
Natural Gas | $48,157 | 8,444 | MMBtu | $5.70 |
TOTAL ENERGY COSTS | $456,374 | |||
RECOMMENDED SAVINGS* | $44,521 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,884 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,945 Cost: $12,879 |
$10,139 | 166,106 | $1,806 | 134 | - | - |
$10,139 166,106 kWh |
$1,806 134 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $6,367 Cost: $6,400 |
- | - | - | - | $6,367 | 1,131 |
- - kWh |
- - kW-months/year |
$6,367 1,131 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $5,586 Cost: - |
$5,586 | 83,333 | - | - | - | - |
$5,586 83,333 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,884 Cost: $4,500 |
$3,279 | 53,712 | $606 | 45 | - | - |
$3,279 53,712 kWh |
$606 45 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7272 INSTALL HEAT PIPES / RAISE COOLING SETPOINT |
Savings: $3,255 Cost: - |
$1,584 | 25,953 | $1,671 | 124 | - | - |
$1,584 25,953 kWh |
$1,671 124 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,250 Cost: - |
$2,374 | 38,883 | $876 | 65 | - | - |
$2,374 38,883 kWh |
$876 65 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,164 Cost: $1,500 |
$3,164 | 51,840 | - | - | - | - |
$3,164 51,840 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,815 Cost: $2,460 |
$1,328 | 21,753 | $487 | 36 | - | - |
$1,328 21,753 kWh |
$487 36 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $1,598 Cost: $2,000 |
- | - | - | - | $1,598 | 280 |
- - kWh |
- - kW-months/year |
$1,598 280 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $1,438 Cost: $928 |
- | - | - | - | $1,438 | 252 |
- - kWh |
- - kW-months/year |
$1,438 252 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7444 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS |
Savings: $1,240 Cost: $748 |
- | - | - | - | $1,240 | 217 |
- - kWh |
- - kW-months/year |
$1,240 217 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $979 Cost: - |
- | - | - | - | $979 | 172 |
- - kWh |
- - kW-months/year |
$979 172 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $44,521 Cost: $31,415 |
$27,454 | 441,580 | $5,446 | 403 | $11,622 | 2,052 | $27,454 441,580 kWh |
$5,446 403 kW-months/year |
$11,622 2,052 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,884 Cost: $4,500 |
$3,279 | 53,712 | $606 | 45 | - | - | $3,279 53,712 kWh |
$606 45 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||