IAC Assessment: WM0213
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WM0213
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Wisconsin, Milwaukee
Assessment Year 2024
Principal Product Cold Formed Steel
NAICS 333517 - Machine Tool Manufacturing
SIC 3541 - Machine Tools, Metal Cutting Types
Sales $10,000,000-$50,000,000
# of Employees 60
Plant Area (Sq.Ft.) 120,000
Annual Production 2,000 Tons
Production Hrs. Annual 5,760
Location (State) WI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $66,608 949,375 kWh $0.07
Electricity Demand $55,357 3,099 kW-months/year $17.86
Electricity Fees $15,353 - $ -
Natural Gas $38,276 4,827 MMBtu $7.93
TOTAL ENERGY COSTS $175,594
RECOMMENDED SAVINGS* $20,579 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas
$ kWh $ kW-months/year $ $ $ MMBtu
01: 2.7491 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS Savings:
$10,341
Cost:
$20,389
- - - - - - $10,341 1,227 -
-
kWh
-
-
kW-months/year
-
-
$
$10,341
1,227
MMBtu
02: 2.7231 USE RADIANT HEATER FOR SPOT HEATING Savings:
$3,521
Cost:
$16,500
- - - - - - $3,521 444 -
-
kWh
-
-
kW-months/year
-
-
$
$3,521
444
MMBtu
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$2,965
Cost:
$267
$2,104 30,054 $861 48 - - - - $2,104
30,054
kWh
$861
48
kW-months/year
-
-
$
-
-
MMBtu
04: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS Savings:
$2,240
Cost:
$2,590
- - - - $2,240 - - - -
-
kWh
-
-
kW-months/year
$2,240
-
$
-
-
MMBtu
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,049
Cost:
$125
$781 11,162 $268 15 - - - - $781
11,162
kWh
$268
15
kW-months/year
-
-
$
-
-
MMBtu
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$463
Cost:
$1,730
$343 4,903 $120 7 - - - - $343
4,903
kWh
$120
7
kW-months/year
-
-
$
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$20,579
Cost:
$41,601
$3,228 46,119 $1,249 70 $2,240 - $13,862 1,671 $3,228
46,119
kWh
$1,249
70
kW-months/year
$2,240
-
$
$13,862
1,671
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas