IAC Assessment: WV0095
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0095
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 1996
Principal Product Plastic Injection Moldings
NAICS n/a
SIC 3544 - Special Dies, Tools, Jigs & Fixtures
Sales $10,000,000-$50,000,000
# of Employees 230
Plant Area (Sq.Ft.) 130,000
Annual Production 3,000,000 Pounds
Production Hrs. Annual 6,120
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $233,001 6,794,549 kWh $0.03
Electricity Demand $275,517 15,067 kW-months/year $18.29
Electricity Fees $(-14,758) - $ -
Natural Gas $69,902 15,703 MMBtu $4.45
TOTAL ENERGY COSTS $563,662
RECOMMENDED SAVINGS* $53,902 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $42,917
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.3137 USE POWER DURING OFF-PEAK PERIODS Savings:
$24,235
Cost:
-
- - $24,235 1,320 - - - - -
-
kWh
$24,235
1,320
kW-months/year
-
-
MMBtu
-
-
$
02: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE Savings:
$4,565
Cost:
$550
$4,565 145,076 - - - - - - $4,565
145,076
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$466
Cost:
$700
- - - - $466 104 - - -
-
kWh
-
-
kW-months/year
$466
104
MMBtu
-
-
$
04: 2.1213 DIRECT WARMEST AIR TO COMBUSTION INTAKE Savings:
$534
Cost:
$2,105
- - - - $534 120 - - -
-
kWh
-
-
kW-months/year
$534
120
MMBtu
-
-
$
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$1,811
Cost:
$2,743
- - - - $1,811 407 - - -
-
kWh
-
-
kW-months/year
$1,811
407
MMBtu
-
-
$
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$580
Cost:
-
- - - - $580 97 - - -
-
kWh
-
-
kW-months/year
$580
97
MMBtu
-
-
$
07: 2.7312 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE Savings:
$8,019
Cost:
$2,940
- - - - $8,019 1,802 - - -
-
kWh
-
-
kW-months/year
$8,019
1,802
MMBtu
-
-
$
08: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$2,432
Cost:
$2,800
$(-46) (-1,465) - - $2,478 557 - - $(-46)
(-1,465)
kWh
-
-
kW-months/year
$2,478
557
MMBtu
-
-
$
09: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$11,260
Cost:
$9,000
- - - - - - $11,260 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$11,260
-
$
TOTAL RECOMMENDED Savings:
$53,902
Cost:
$20,838
$4,519 143,611 $24,235 1,320 $13,888 3,087 $11,260 - $4,519
143,611
kWh
$24,235
1,320
kW-months/year
$13,888
3,087
MMBtu
$11,260
-
$
TOTAL IMPLEMENTED Savings:
$42,917
Cost:
$12,993
$4,565 145,076 $24,235 1,320 $2,857 608 $11,260 - $4,565
145,076
kWh
$24,235
1,320
kW-months/year
$2,857
608
MMBtu
$11,260
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes