IAC logo
IAC Assessment: WV0152
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0152
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 1998
Principal Product Flat glass
NAICS n/a
SIC 3211 - Flat Glass
Sales $10,000,000-$50,000,000
# of Employees 110
Plant Area (Sq.Ft.) 225,000
Annual Production 500 Thousand Feet
Production Hrs. Annual 6,240
Location (State) PA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $329,041 8,627,198 kWh $0.04
Electricity Demand $223,882 20,675 kW-months/year $10.83
Electricity Fees $11,261 - $ -
Natural Gas $132,021 35,163 MMBtu $3.75
TOTAL ENERGY COSTS $696,205
RECOMMENDED SAVINGS* $50,362 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $26,815
#|Description Savings
Cost
Status Electricity Usage Natural Gas Other Gas Solid Waste (non-haz) Solid Waste (haz) Administrative Changes Electricity Usage Natural Gas Other Gas Solid Waste (non-haz) Solid Waste (haz) Administrative Changes
$ kWh $ MMBtu $ MMBtu $ lb $ lb $ $
01: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT Savings:
$6,254
Cost:
$2,580
$6,254 158,558 - - - - - - - - - - $6,254
158,558
kWh
-
-
MMBtu
-
-
MMBtu
-
-
lb
-
-
lb
-
-
$
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$758
Cost:
$700
- - $758 202 - - - - - - - - -
-
kWh
$758
202
MMBtu
-
-
MMBtu
-
-
lb
-
-
lb
-
-
$
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$5,558
Cost:
$2,600
- - $5,558 1,482 - - - - - - - - -
-
kWh
$5,558
1,482
MMBtu
-
-
MMBtu
-
-
lb
-
-
lb
-
-
$
04: 2.2511 INSULATE BARE EQUIPMENT Savings:
$447
Cost:
$171
- - $447 119 - - - - - - - - -
-
kWh
$447
119
MMBtu
-
-
MMBtu
-
-
lb
-
-
lb
-
-
$
05: 2.2511 INSULATE BARE EQUIPMENT Savings:
$236
Cost:
$732
- - $236 63 - - - - - - - - -
-
kWh
$236
63
MMBtu
-
-
MMBtu
-
-
lb
-
-
lb
-
-
$
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,785
Cost:
$1,355
- - $1,785 476 - - - - - - - - -
-
kWh
$1,785
476
MMBtu
-
-
MMBtu
-
-
lb
-
-
lb
-
-
$
07: 2.1331 BURN A LESS EXPENSIVE GRADE OF FUEL Savings:
$9,550
Cost:
$8,400
- - - - $9,550 - - - - - - - -
-
kWh
-
-
MMBtu
$9,550
-
MMBtu
-
-
lb
-
-
lb
-
-
$
08: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$960
Cost:
$50
- - - - - - $960 - - - - - -
-
kWh
-
-
MMBtu
-
-
MMBtu
$960
-
lb
-
-
lb
-
-
$
09: 3.5318 RECYCLE FLUORESCENT LAMPS Savings:
$400
Cost:
$45
- - - - - - - - $400 - - - -
-
kWh
-
-
MMBtu
-
-
MMBtu
-
-
lb
$400
-
lb
-
-
$
10: 4.5140 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS Savings:
$24,414
Cost:
$3,000
- - - - - - - - - - $24,414 - -
-
kWh
-
-
MMBtu
-
-
MMBtu
-
-
lb
-
-
lb
$24,414
-
$
TOTAL RECOMMENDED Savings:
$50,362
Cost:
$19,633
$6,254 158,558 $8,784 2,342 $9,550 - $960 - $400 - $24,414 - $6,254
158,558
kWh
$8,784
2,342
MMBtu
$9,550
-
MMBtu
$960
-
lb
$400
-
lb
$24,414
-
$
TOTAL IMPLEMENTED Savings:
$26,815
Cost:
$4,653
- - $1,441 384 - - $960 - - - $24,414 - -
-
kWh
$1,441
384
MMBtu
-
-
MMBtu
$960
-
lb
-
-
lb
$24,414
-
$
Savings
Cost
$ kWh $ MMBtu $ MMBtu $ lb $ lb $ $
Electricity Usage Natural Gas Other Gas Solid Waste (non-haz) Solid Waste (haz) Administrative Changes Electricity Usage Natural Gas Other Gas Solid Waste (non-haz) Solid Waste (haz) Administrative Changes