Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2000 |
Principal Product | Corrugated Paperboard |
NAICS | n/a |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 53 |
Plant Area (Sq.Ft.) | 72,000 |
Annual Production | 300,000 Thousand Feet |
Production Hrs. Annual | 4,680 |
Location (State) | WV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $105,076 | 1,706,038 | kWh | $0.06 |
Natural Gas | $77,550 | 21,596 | MMBtu | $3.59 |
TOTAL ENERGY COSTS | $182,626 | |||
RECOMMENDED SAVINGS* | $37,545 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $35,269 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Primary Product | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $6,939 Cost: $3,252 |
- | - | $6,939 | 1,933 | - | - | - | - |
- - kWh |
$6,939 1,933 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $808 Cost: $275 |
- | - | $808 | 225 | - | - | - | - |
- - kWh |
$808 225 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $937 Cost: $500 |
- | - | $937 | 261 | - | - | - | - |
- - kWh |
$937 261 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $2,348 Cost: $1,368 |
- | - | $2,348 | 327 | - | - | - | - |
- - kWh |
$2,348 327 MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $4,494 Cost: $664 |
$4,494 | 72,978 | - | - | - | - | - | - |
$4,494 72,978 kWh |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $531 Cost: $154 |
$531 | 8,499 | - | - | - | - | - | - |
$531 8,499 kWh |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $908 Cost: $912 |
$908 | 14,654 | - | - | - | - | - | - |
$908 14,654 kWh |
- - MMBtu |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $4,000 Cost: $863 |
- | - | - | - | $4,000 | - | - | - |
- - kWh |
- - MMBtu |
$4,000 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $2,880 Cost: $100 |
- | - | - | - | $2,880 | - | - | - |
- - kWh |
- - MMBtu |
$2,880 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $2,000 Cost: $400 |
- | - | - | - | $2,000 | - | - | - |
- - kWh |
- - MMBtu |
$2,000 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.621 USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES |
Savings: $11,700 Cost: $500 |
- | - | - | - | - | - | $11,700 | - |
- - kWh |
- - MMBtu |
- - lb |
$11,700 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $37,545 Cost: $8,988 |
$5,933 | 96,131 | $11,032 | 2,746 | $8,880 | - | $11,700 | - | $5,933 96,131 kWh |
$11,032 2,746 MMBtu |
$8,880 - lb |
$11,700 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $35,269 Cost: $8,059 |
$5,402 | 87,632 | $9,287 | 2,260 | $8,880 | - | $11,700 | - | $5,402 87,632 kWh |
$9,287 2,260 MMBtu |
$8,880 - lb |
$11,700 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Solid Waste (non-haz) | Primary Product | Electricity Usage | Natural Gas | Solid Waste (non-haz) | Primary Product |