Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2001 |
Principal Product | Lithographic sheets |
NAICS | n/a |
SIC | 3499 - Fabricated Metal Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 176 |
Plant Area (Sq.Ft.) | 158,000 |
Annual Production | 115,000 Tons |
Production Hrs. Annual | 6,984 |
Location (State) | WV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $394,423 | 14,096,000 | kWh | $0.03 |
Electricity Demand | $249,871 | 30,055 | kW-months/year | $8.31 |
Natural Gas | $1,234,310 | 197,979 | MMBtu | $6.23 |
TOTAL ENERGY COSTS | $1,878,604 | |||
RECOMMENDED SAVINGS* | $196,114 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $58,929 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $4,919 Cost: $750 |
$2,897 | 101,085 | $2,022 | 18 | - | - | - | - | - | - | - | - |
$2,897 101,085 kWh |
$2,022 18 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $1,589 Cost: $1,980 |
$1,074 | 37,504 | $515 | 5 | - | - | - | - | - | - | - | - |
$1,074 37,504 kWh |
$515 5 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $913 Cost: $100 |
$587 | 20,510 | $326 | 3 | - | - | - | - | - | - | - | - |
$587 20,510 kWh |
$326 3 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE |
Savings: $704 Cost: $50 |
$453 | 15,822 | $251 | 2 | - | - | - | - | - | - | - | - |
$453 15,822 kWh |
$251 2 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2696 USE EXCESS COLD PROCESS FLUID FOR INDUSTRIAL COOLING NEEDS |
Savings: $603 Cost: $390 |
$386 | 13,478 | $217 | 2 | - | - | - | - | - | - | - | - |
$386 13,478 kWh |
$217 2 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $275 Cost: $112 |
- | - | - | - | $275 | 44 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$275 44 MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM |
Savings: $31,855 Cost: $2,000 |
$21,552 | 751,545 | $10,303 | 108 | - | - | - | - | - | - | - | - |
$21,552 751,545 kWh |
$10,303 108 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $12,200 Cost: $1,000 |
$7,820 | 273,076 | $4,380 | 39 | - | - | - | - | - | - | - | - |
$7,820 273,076 kWh |
$4,380 39 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,150 Cost: $2,910 |
$663 | 23,147 | $487 | 5 | - | - | - | - | - | - | - | - |
$663 23,147 kWh |
$487 5 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $16,267 Cost: $3,000 |
- | - | - | - | $16,267 | 2,611 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$16,267 2,611 MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,814 Cost: $100 |
$3,935 | 137,417 | $1,879 | 20 | - | - | - | - | - | - | - | - |
$3,935 137,417 kWh |
$1,879 20 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 3.3111 ADJUST PH FOR NEUTRALIZATION |
Savings: $8,625 Cost: $13,725 |
- | - | - | - | - | - | $8,625 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$8,625 - gal |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $1,200 Cost: $75 |
- | - | - | - | - | - | - | - | $1,200 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$1,200 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $110,000 Cost: $85,000 |
- | - | - | - | - | - | - | - | - | - | $110,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$110,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $196,114 Cost: $111,192 |
$39,367 | 1,373,584 | $20,380 | 202 | $16,542 | 2,655 | $8,625 | - | $1,200 | - | $110,000 | - | $39,367 1,373,584 kWh |
$20,380 202 kW-months/year |
$16,542 2,655 MMBtu |
$8,625 - gal |
$1,200 - lb |
$110,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $58,929 Cost: $7,437 |
$37,840 | 1,320,258 | $19,614 | 195 | $275 | 44 | - | - | $1,200 | - | - | - | $37,840 1,320,258 kWh |
$19,614 195 kW-months/year |
$275 44 MMBtu |
- - gal |
$1,200 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (non-haz) | Administrative Changes |