IAC Assessment: WV0281
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0281
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 2003
Principal Product Dried Lumber
NAICS 321999 - All Other Miscellaneous Wood Product Manufacturing
SIC 2421 - Sawmills And Planing Mills, General
Sales <$500,000
# of Employees 8
Plant Area (Sq.Ft.) 10,000
Annual Production 4,000 Thousand Feet
Production Hrs. Annual 8,736
Location (State) WV
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $26,362 362,631 kWh $0.07
Electricity Fees $1,317 - $ -
Natural Gas $80,174 9,993 MMBtu $8.02
TOTAL ENERGY COSTS $107,853
RECOMMENDED SAVINGS* $69,131 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,755
#|Description Savings
Cost
Status Electricity Usage Natural Gas Personnel Changes Administrative Changes Electricity Usage Natural Gas Personnel Changes Administrative Changes
$ kWh $ MMBtu $ $ $ $
01: 2.1331 BURN A LESS EXPENSIVE GRADE OF FUEL Savings:
$52,226
Cost:
$153,000
- - - - - - $52,226 - -
-
kWh
-
-
MMBtu
-
-
$
$52,226
-
$
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$12,150
Cost:
$1,695
- - $12,150 1,515 - - - - -
-
kWh
$12,150
1,515
MMBtu
-
-
$
-
-
$
03: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$1,940
Cost:
$240
$1,990 26,077 - - $(-50) - - - $1,990
26,077
kWh
-
-
MMBtu
$(-50)
-
$
-
-
$
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$1,652
Cost:
$1,000
- - $1,652 206 - - - - -
-
kWh
$1,652
206
MMBtu
-
-
$
-
-
$
05: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,163
Cost:
$38
- - $1,163 145 - - - - -
-
kWh
$1,163
145
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$69,131
Cost:
$155,973
$1,990 26,077 $14,965 1,866 $(-50) - $52,226 - $1,990
26,077
kWh
$14,965
1,866
MMBtu
$(-50)
-
$
$52,226
-
$
TOTAL IMPLEMENTED Savings:
$4,755
Cost:
$1,278
$1,990 26,077 $2,815 351 $(-50) - - - $1,990
26,077
kWh
$2,815
351
MMBtu
$(-50)
-
$
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $ $ $
Electricity Usage Natural Gas Personnel Changes Administrative Changes Electricity Usage Natural Gas Personnel Changes Administrative Changes