IAC Assessment: WV0325
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0325
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 2005
Principal Product Rubber Seals for Automotive Vehicles
NAICS 339991 - Gasket, Packing, and Sealing Device Manufacturing
SIC 3053 - Gaskets, Packing And Sealing Devices
Sales $5,000,000-$10,000,000
# of Employees 100
Plant Area (Sq.Ft.) 155,000
Annual Production 2,204,623 Pounds
Production Hrs. Annual 6,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $260,035 4,031,100 kWh $0.06
Electricity Fees $11,783 - $ -
Natural Gas $54,816 6,008 MMBtu $9.12
TOTAL ENERGY COSTS $326,634
RECOMMENDED SAVINGS* $58,033 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $26,269
#|Description Savings
Cost
Status Electricity Usage Electricity Fees Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Fees Natural Gas Personnel Changes Ancillary Material Cost
$ kWh $ $ $ MMBtu $ $ $ $
01: 2.7231 USE RADIANT HEATER FOR SPOT HEATING Savings:
$16,088
Cost:
$12,504
- - - - $16,088 1,764 - - - - -
-
kWh
-
-
$
$16,088
1,764
MMBtu
-
-
$
-
-
$
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$10,956
Cost:
$11,550
- - $10,956 - - - - - - - -
-
kWh
$10,956
-
$
-
-
MMBtu
-
-
$
-
-
$
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$7,144
Cost:
$662
$7,144 110,880 - - - - - - - - $7,144
110,880
kWh
-
-
$
-
-
MMBtu
-
-
$
-
-
$
04: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$7,050
Cost:
$653
- - - - $7,050 773 - - - - -
-
kWh
-
-
$
$7,050
773
MMBtu
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,009
Cost:
-
$5,009 77,880 - - - - - - - - $5,009
77,880
kWh
-
-
$
-
-
MMBtu
-
-
$
-
-
$
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$3,529
Cost:
$408
- - - - $3,529 387 - - - - -
-
kWh
-
-
$
$3,529
387
MMBtu
-
-
$
-
-
$
07: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$2,990
Cost:
$257
$3,242 50,279 - - - - $(-252) - - - $3,242
50,279
kWh
-
-
$
-
-
MMBtu
$(-252)
-
$
-
-
$
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,637
Cost:
$420
$2,003 31,063 - - - - $(-126) - $(-240) - $2,003
31,063
kWh
-
-
$
-
-
MMBtu
$(-126)
-
$
$(-240)
-
$
09: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$851
Cost:
$426
$851 13,176 - - - - - - - - $851
13,176
kWh
-
-
$
-
-
MMBtu
-
-
$
-
-
$
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$832
Cost:
$2,612
$832 12,882 - - - - - - - - $832
12,882
kWh
-
-
$
-
-
MMBtu
-
-
$
-
-
$
11: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD Savings:
$775
Cost:
$521
$775 12,055 - - - - - - - - $775
12,055
kWh
-
-
$
-
-
MMBtu
-
-
$
-
-
$
12: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$756
Cost:
$260
$756 11,850 - - - - - - - - $756
11,850
kWh
-
-
$
-
-
MMBtu
-
-
$
-
-
$
13: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$416
Cost:
$276
$416 6,362 - - - - - - - - $416
6,362
kWh
-
-
$
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$58,033
Cost:
$30,549
$21,028 326,427 $10,956 - $26,667 2,924 $(-378) - $(-240) - $21,028
326,427
kWh
$10,956
-
$
$26,667
2,924
MMBtu
$(-378)
-
$
$(-240)
-
$
TOTAL IMPLEMENTED Savings:
$26,269
Cost:
$5,290
$19,837 308,010 - - $7,050 773 $(-378) - $(-240) - $19,837
308,010
kWh
-
-
$
$7,050
773
MMBtu
$(-378)
-
$
$(-240)
-
$
Savings
Cost
$ kWh $ $ $ MMBtu $ $ $ $
Electricity Usage Electricity Fees Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Fees Natural Gas Personnel Changes Ancillary Material Cost