IAC Assessment: WV0410
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0410
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 2010
Principal Product Printed Circuit Board
NAICS 334412 - Bare Printed Circuit Board Manufacturing
SIC 3672 - Printed Circuit Boards
Sales $10,000,000-$50,000,000
# of Employees 104
Plant Area (Sq.Ft.) 65,000
Annual Production 1,000,000 Pieces
Production Hrs. Annual 4,590
Location (State) MD
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $275,922 2,656,830 kWh $0.10
Electricity Demand $13,274 5,451 kW-months/year $2.44
Natural Gas $15,912 1,469 MMBtu $10.83
TOTAL ENERGY COSTS $305,108
RECOMMENDED SAVINGS* $110,734 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $100,875
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes
$ kWh $ kW-months/year $ $ $ MMBtu $ $
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$92,924
Cost:
-
- - - - $92,924 - - - - - -
-
kWh
-
-
kW-months/year
$92,924
-
$
-
-
MMBtu
-
-
$
02: 2.7229 AIR CONDITION ONLY SPACE NECESSARY Savings:
$6,499
Cost:
$900
$4,232 40,727 $144 59 - - $2,123 196 - - $4,232
40,727
kWh
$144
59
kW-months/year
-
-
$
$2,123
196
MMBtu
-
-
$
03: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$3,551
Cost:
$2,200
$1,721 16,572 - - - - $1,830 169 - - $1,721
16,572
kWh
-
-
kW-months/year
-
-
$
$1,830
169
MMBtu
-
-
$
04: 2.4312 IMPROVE LUBRICATION PRACTICES Savings:
$1,907
Cost:
$618
$1,850 17,806 $57 23 - - - - - - $1,850
17,806
kWh
$57
23
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
05: 2.7231 USE RADIANT HEATER FOR SPOT HEATING Savings:
$1,430
Cost:
$5,800
- - - - - - $1,430 132 - - -
-
kWh
-
-
kW-months/year
-
-
$
$1,430
132
MMBtu
-
-
$
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,273
Cost:
$210
$1,200 11,545 $73 30 - - - - - - $1,200
11,545
kWh
$73
30
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
07: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING Savings:
$1,222
Cost:
$3,100
- - - - - - $1,722 159 $(-500) - -
-
kWh
-
-
kW-months/year
-
-
$
$1,722
159
MMBtu
$(-500)
-
$
08: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$1,020
Cost:
$67
$961 9,253 $59 24 - - - - - - $961
9,253
kWh
$59
24
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
09: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$563
Cost:
$274
- - - - - - $563 52 - - -
-
kWh
-
-
kW-months/year
-
-
$
$563
52
MMBtu
-
-
$
10: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$200
Cost:
$20
$188 1,727 $12 5 - - - - - - $188
1,727
kWh
$12
5
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
11: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$145
Cost:
$440
$138 1,333 $7 3 - - - - - - $138
1,333
kWh
$7
3
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$110,734
Cost:
$13,629
$10,290 98,963 $352 144 $92,924 - $7,668 708 $(-500) - $10,290
98,963
kWh
$352
144
kW-months/year
$92,924
-
$
$7,668
708
MMBtu
$(-500)
-
$
TOTAL IMPLEMENTED Savings:
$100,875
Cost:
$3,115
$5,920 56,903 $201 82 $92,924 - $1,830 169 - - $5,920
56,903
kWh
$201
82
kW-months/year
$92,924
-
$
$1,830
169
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes Electricity Usage Electricity Demand Electricity Fees Natural Gas Personnel Changes