IAC Assessment: WV0419
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0419
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 2010
Principal Product Transformers
NAICS 335311 - Power, Distribution, and Specialty Transformer Manufacturing
SIC 3612 - Transformers, Except Electronic
Sales $50,000,000-$100,000,000
# of Employees 311
Plant Area (Sq.Ft.) 700,000
Annual Production 130 Pieces
Production Hrs. Annual 3,744
Location (State) PA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $554,848 13,471,554 kWh $0.04
Electricity Demand $177,315 33,497 kW-months/year $5.29
Electricity Fees $1,838 - $ -
Natural Gas $737,772 73,846 MMBtu $9.99
TOTAL ENERGY COSTS $1,471,773
RECOMMENDED SAVINGS* $174,881 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $67,036
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Increase in Production Electricity Usage Electricity Demand Natural Gas Increase in Production
$ kWh $ kW-months/year $ MMBtu $ %
01: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$80,000
Cost:
$53,870
- - - - - - $80,000 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$80,000
-
%
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$66,262
Cost:
$161,162
$48,847 1,185,599 $17,415 3,292 - - - - $48,847
1,185,599
kWh
$17,415
3,292
kW-months/year
-
-
MMBtu
-
-
%
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$27,845
Cost:
$59,247
$(-1,208) (-29,327) $(-497) (-94) $29,550 2,958 - - $(-1,208)
(-29,327)
kWh
$(-497)
(-94)
kW-months/year
$29,550
2,958
MMBtu
-
-
%
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$774
Cost:
$528
$658 15,978 $116 22 - - - - $658
15,978
kWh
$116
22
kW-months/year
-
-
MMBtu
-
-
%
TOTAL RECOMMENDED Savings:
$174,881
Cost:
$274,807
$48,297 1,172,250 $17,034 3,220 $29,550 2,958 $80,000 - $48,297
1,172,250
kWh
$17,034
3,220
kW-months/year
$29,550
2,958
MMBtu
$80,000
-
%
TOTAL IMPLEMENTED Savings:
$67,036
Cost:
$161,690
$49,505 1,201,577 $17,531 3,314 - - - - $49,505
1,201,577
kWh
$17,531
3,314
kW-months/year
-
-
MMBtu
-
-
%
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ %
Electricity Usage Electricity Demand Natural Gas Increase in Production Electricity Usage Electricity Demand Natural Gas Increase in Production