Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2011 |
Principal Product | Storm Doors |
NAICS | 332321 - Metal Window and Door Manufacturing |
SIC | 3442 - Metal Doors, Sash, And Trim |
Sales | $5,000,000-$10,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 350,000 |
Annual Production | 750,000 Pieces |
Production Hrs. Annual | 4,500 |
Location (State) | VA |
View Case Study |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $202,367 | 3,359,044 | kWh | $0.06 |
Electricity Demand | $77,296 | 9,674 | kW-months/year | $7.99 |
Other Gas | $29,584 | 1,652 | MMBtu | $17.91 |
TOTAL ENERGY COSTS | $309,247 | |||
RECOMMENDED SAVINGS* | $63,740 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $54,182 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Gas | Personnel Changes | Electricity Usage | Electricity Demand | Other Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $35,791 Cost: $69,419 |
$26,443 | 438,885 | $9,348 | 1,170 | - | - | - | - |
$26,443 438,885 kWh |
$9,348 1,170 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,832 Cost: $363 |
$5,787 | 96,044 | $2,045 | 256 | - | - | - | - |
$5,787 96,044 kWh |
$2,045 256 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $4,170 Cost: $5,180 |
$3,107 | 51,575 | $1,063 | 133 | - | - | - | - |
$3,107 51,575 kWh |
$1,063 133 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $3,937 Cost: $18,000 |
$3,304 | 54,845 | $633 | 79 | - | - | - | - |
$3,304 54,845 kWh |
$633 79 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $2,985 Cost: $613 |
$2,522 | 41,856 | $895 | 112 | - | - | $(-432) | - |
$2,522 41,856 kWh |
$895 112 kW-months/year |
- - MMBtu |
$(-432) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,934 Cost: $5,194 |
$1,942 | 32,230 | $992 | 124 | - | - | - | - |
$1,942 32,230 kWh |
$992 124 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $2,803 Cost: $1,613 |
$2,068 | 34,324 | $735 | 92 | - | - | - | - |
$2,068 34,324 kWh |
$735 92 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,837 Cost: $1,119 |
$1,358 | 22,535 | $479 | 60 | - | - | - | - |
$1,358 22,535 kWh |
$479 60 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $1,451 Cost: $4,200 |
- | - | - | - | $1,451 | 81 | - | - |
- - kWh |
- - kW-months/year |
$1,451 81 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $63,740 Cost: $105,701 |
$46,531 | 772,294 | $16,190 | 2,026 | $1,451 | 81 | $(-432) | - | $46,531 772,294 kWh |
$16,190 2,026 kW-months/year |
$1,451 81 MMBtu |
$(-432) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $54,182 Cost: $78,321 |
$40,120 | 665,874 | $14,494 | 1,814 | - | - | $(-432) | - | $40,120 665,874 kWh |
$14,494 1,814 kW-months/year |
- - MMBtu |
$(-432) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Gas | Personnel Changes | Electricity Usage | Electricity Demand | Other Gas | Personnel Changes |