Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2015 |
Principal Product | Metal Finishing |
NAICS | 332813 - Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471 - Plating And Polishing |
Sales | $1,000,000-$5,000,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 20,000 |
Annual Production | 8,000,000 Pounds |
Production Hrs. Annual | 3,952 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $65,676 | 590,740 | kWh | $0.11 |
Electricity Demand | $14,595 | 2,112 | kW-months/year | $6.91 |
Natural Gas | $107,288 | 19,293 | MMBtu | $5.56 |
TOTAL ENERGY COSTS | $187,559 | |||
RECOMMENDED SAVINGS* | $32,832 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,552 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2123 INSULATE FEEDWATER TANK |
Savings: $13,405 Cost: $6,253 |
- | - | - | - | $13,405 | 2,411 | - | - |
- - kWh |
- - kW-months/year |
$13,405 2,411 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $4,569 Cost: $1,700 |
- | - | - | - | $4,954 | 891 | $(-385) | - |
- - kWh |
- - kW-months/year |
$4,954 891 MMBtu |
$(-385) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $4,682 Cost: $1,278 |
$3,914 | 35,199 | $768 | 111 | - | - | - | - |
$3,914 35,199 kWh |
$768 111 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1221 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES |
Savings: $4,181 Cost: $11,220 |
- | - | - | - | $4,181 | 752 | - | - |
- - kWh |
- - kW-months/year |
$4,181 752 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,835 Cost: $920 |
$1,544 | 13,884 | $291 | 42 | - | - | - | - |
$1,544 13,884 kWh |
$291 42 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,694 Cost: $6,400 |
$1,424 | 12,806 | $270 | 39 | - | - | - | - |
$1,424 12,806 kWh |
$270 39 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $1,310 Cost: $1,175 |
$1,206 | 10,841 | $104 | 15 | - | - | - | - |
$1,206 10,841 kWh |
$104 15 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $975 Cost: $3,180 |
$795 | 7,148 | $180 | 26 | - | - | - | - |
$795 7,148 kWh |
$180 26 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $181 Cost: $35 |
$153 | 1,379 | $28 | 4 | - | - | - | - |
$153 1,379 kWh |
$28 4 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,832 Cost: $32,161 |
$9,036 | 81,257 | $1,641 | 237 | $22,540 | 4,054 | $(-385) | - | $9,036 81,257 kWh |
$1,641 237 kW-months/year |
$22,540 4,054 MMBtu |
$(-385) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,552 Cost: $8,288 |
$7,612 | 68,451 | $1,371 | 198 | $4,954 | 891 | $(-385) | - | $7,612 68,451 kWh |
$1,371 198 kW-months/year |
$4,954 891 MMBtu |
$(-385) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes |