Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2016 |
Principal Product | Thermoplastic resin |
NAICS | 325211 - Plastics Material and Resin Manufacturing |
SIC | 2821 - Plastics Materials And Resins |
Sales | $10,000,000-$50,000,000 |
# of Employees | 65 |
Plant Area (Sq.Ft.) | 345,000 |
Annual Production | 35,000,000 Pounds |
Production Hrs. Annual | 7,488 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $282,293 | 4,028,960 | kWh | $0.07 |
Electricity Demand | $37,701 | 5,532 | kW-months/year | $6.82 |
TOTAL ENERGY COSTS | $319,994 | |||
RECOMMENDED SAVINGS* | $23,550 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,790 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,812 Cost: $8,931 |
$5,891 | 84,042 | $921 | 135 | - | - |
$5,891 84,042 kWh |
$921 135 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $4,153 Cost: $511 |
$3,594 | 51,275 | $559 | 82 | - | - |
$3,594 51,275 kWh |
$559 82 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4157 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM |
Savings: $3,206 Cost: $1,000 |
$3,434 | 48,983 | $532 | 78 | $(-760) | - |
$3,434 48,983 kWh |
$532 78 kW-months/year |
$(-760) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $2,918 Cost: $4,500 |
$2,918 | 41,628 | - | - | - | - |
$2,918 41,628 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,030 Cost: $6,200 |
$2,030 | 28,954 | - | - | - | - |
$2,030 28,954 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $1,538 Cost: $578 |
$1,486 | 21,195 | $232 | 34 | $(-180) | - |
$1,486 21,195 kWh |
$232 34 kW-months/year |
$(-180) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,622 Cost: $2,120 |
$1,363 | 19,437 | $259 | 38 | - | - |
$1,363 19,437 kWh |
$259 38 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $691 Cost: $30 |
$596 | 8,497 | $95 | 14 | - | - |
$596 8,497 kWh |
$95 14 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $320 Cost: $298 |
$279 | 3,981 | $41 | 6 | - | - |
$279 3,981 kWh |
$41 6 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $260 Cost: $138 |
$226 | 3,221 | $34 | 5 | - | - |
$226 3,221 kWh |
$34 5 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $23,550 Cost: $24,306 |
$21,817 | 311,213 | $2,673 | 392 | $(-940) | - | $21,817 311,213 kWh |
$2,673 392 kW-months/year |
$(-940) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,790 Cost: $4,675 |
$10,978 | 156,589 | $1,752 | 257 | $(-940) | - | $10,978 156,589 kWh |
$1,752 257 kW-months/year |
$(-940) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes |