Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2017 |
Principal Product | Hand Tools |
NAICS | 332216 - Saw Blade and Handtool Manufacturing |
SIC | 3423 - Hand And Edge Tools, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 14 |
Plant Area (Sq.Ft.) | 900,000 |
Annual Production | 25,550 Units |
Production Hrs. Annual | 2,000 |
Location (State) | WV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $25,184 | 336,487 | kWh | $0.07 |
Electricity Demand | $19,153 | 2,105 | kW-months/year | $9.10 |
Electricity Fees | $252 | - | $ | - |
Natural Gas | $50,170 | 8,837 | MMBtu | $5.68 |
Other Gas | $8,952 | 414 | MMBtu | $21.62 |
TOTAL ENERGY COSTS | $103,873 | |||
RECOMMENDED SAVINGS* | $35,797 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,408 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $23,992 Cost: $112,000 |
- | - | - | - | $23,992 | 4,224 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$23,992 4,224 MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,431 Cost: $10,658 |
$3,138 | 41,953 | $2,293 | 252 | - | - | - | - | - | - | - | - |
$3,138 41,953 kWh |
$2,293 252 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,017 Cost: $210 |
$2,324 | 31,063 | $1,693 | 186 | - | - | - | - | - | - | - | - |
$2,324 31,063 kWh |
$1,693 186 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,097 Cost: - |
$624 | 8,344 | $473 | 52 | - | - | - | - | - | - | - | - |
$624 8,344 kWh |
$473 52 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $496 Cost: $50 |
$287 | 3,843 | $209 | 23 | - | - | - | - | - | - | - | - |
$287 3,843 kWh |
$209 23 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $397 Cost: $1,500 |
$397 | 5,302 | - | - | - | - | - | - | - | - | - | - |
$397 5,302 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.4151 MINIMIZE WATER USAGE |
Savings: $239 Cost: $1,050 |
- | - | - | - | - | - | $96 | 18 | $162 | 18 | $(-19) | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$96 18 Tgal |
$162 18 Tgal |
$(-19) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $128 Cost: $594 |
$160 | 2,134 | $118 | 13 | - | - | - | - | - | - | $(-150) | - |
$160 2,134 kWh |
$118 13 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
$(-150) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $35,797 Cost: $126,062 |
$6,930 | 92,639 | $4,786 | 526 | $23,992 | 4,224 | $96 | 18 | $162 | 18 | $(-169) | - | $6,930 92,639 kWh |
$4,786 526 kW-months/year |
$23,992 4,224 MMBtu |
$96 18 Tgal |
$162 18 Tgal |
$(-169) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,408 Cost: $12,562 |
$6,533 | 87,337 | $4,786 | 526 | - | - | $96 | 18 | $162 | 18 | $(-169) | - | $6,533 87,337 kWh |
$4,786 526 kW-months/year |
- - MMBtu |
$96 18 Tgal |
$162 18 Tgal |
$(-169) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Administrative Changes |