IAC Assessment: WV0569
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0569
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 2019
Principal Product Steel
NAICS 332999 - All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3441 - Fabricated Structural Metal
Sales $10,000,000-$50,000,000
# of Employees 82
Plant Area (Sq.Ft.) 85,000
Annual Production 4,800 Tons
Production Hrs. Annual 4,420
Location (State) WV
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $87,713 1,237,440 kWh $0.07
Electricity Demand $30,203 4,139 kW-months/year $7.30
Electricity Fees $9,767 - $ -
Natural Gas $1,019 37 MMBtu $27.54
TOTAL ENERGY COSTS $128,702
RECOMMENDED SAVINGS* $88,444 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $21,713
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$40,139
Cost:
$8,050
$137 1,931 - - $2 0 - - $40,000 - $137
1,931
kWh
-
-
kW-months/year
$2
0
MMBtu
-
-
$
$40,000
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$18,808
Cost:
$15,281
$14,136 199,374 $4,672 640 - - - - - - $14,136
199,374
kWh
$4,672
640
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
03: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$13,389
Cost:
$48,000
$10,462 147,562 $2,927 401 - - - - - - $10,462
147,562
kWh
$2,927
401
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
04: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$5,281
Cost:
$4,000
$5,281 74,481 - - - - - - - - $5,281
74,481
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$5,167
Cost:
$5,053
$5,167 72,886 - - - - - - - - $5,167
72,886
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
06: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT Savings:
$2,755
Cost:
$6,300
$1,339 18,882 $1,416 194 - - - - - - $1,339
18,882
kWh
$1,416
194
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$1,147
Cost:
$188
$1,147 16,184 - - - - - - - - $1,147
16,184
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$797
Cost:
$25
$622 8,775 $175 24 - - - - - - $622
8,775
kWh
$175
24
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$592
Cost:
$427
$461 6,500 $131 18 - - - - - - $461
6,500
kWh
$131
18
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
10: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$369
Cost:
$521
$445 6,271 $124 17 - - $(-200) - - - $445
6,271
kWh
$124
17
kW-months/year
-
-
MMBtu
$(-200)
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$88,444
Cost:
$87,845
$39,197 552,846 $9,445 1,294 $2 0 $(-200) - $40,000 - $39,197
552,846
kWh
$9,445
1,294
kW-months/year
$2
0
MMBtu
$(-200)
-
$
$40,000
-
$
TOTAL IMPLEMENTED Savings:
$21,713
Cost:
$16,442
$16,811 237,104 $5,102 699 - - $(-200) - - - $16,811
237,104
kWh
$5,102
699
kW-months/year
-
-
MMBtu
$(-200)
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost