IAC Assessment: WV0595
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WV0595
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center West Virginia University
Assessment Year 2020
Principal Product Manufacturing Custom Metal
NAICS 332710 - Machine Shops
SIC 3599 - Industrial Machinery, Nec
Sales $1,000,000-$5,000,000
# of Employees 15
Plant Area (Sq.Ft.) 15,000
Annual Production 400,000 Units
Production Hrs. Annual 2,652
Location (State) WV
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $56,140 1,303,830 kWh $0.04
Electricity Demand $39,839 2,924 kW-months/year $13.62
Natural Gas $19,301 2,499 MMBtu $7.72
TOTAL ENERGY COSTS $115,280
RECOMMENDED SAVINGS* $14,763 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,848
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Electricity Usage Electricity Demand Natural Gas Personnel Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER Savings:
$7,138
Cost:
$5,700
- - $7,138 525 - - - - -
-
kWh
$7,138
525
kW-months/year
-
-
MMBtu
-
-
$
02: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$2,478
Cost:
$12,144
$1,022 23,708 $1,456 107 - - - - $1,022
23,708
kWh
$1,456
107
kW-months/year
-
-
MMBtu
-
-
$
03: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,313
Cost:
$6,099
- - - - $1,313 171 - - -
-
kWh
-
-
kW-months/year
$1,313
171
MMBtu
-
-
$
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$1,299
Cost:
$4,225
$(-83) (-1,928) - - $1,382 179 - - $(-83)
(-1,928)
kWh
-
-
kW-months/year
$1,382
179
MMBtu
-
-
$
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,263
Cost:
$3,355
$882 20,457 $381 28 - - - - $882
20,457
kWh
$381
28
kW-months/year
-
-
MMBtu
-
-
$
06: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$650
Cost:
$1,100
- - - - $778 98 $(-128) - -
-
kWh
-
-
kW-months/year
$778
98
MMBtu
$(-128)
-
$
07: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$315
Cost:
$406
$199 4,606 $286 21 - - $(-170) - $199
4,606
kWh
$286
21
kW-months/year
-
-
MMBtu
$(-170)
-
$
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$188
Cost:
$305
$79 1,840 $109 8 - - - - $79
1,840
kWh
$109
8
kW-months/year
-
-
MMBtu
-
-
$
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$119
Cost:
$85
$51 1,179 $68 5 - - - - $51
1,179
kWh
$68
5
kW-months/year
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$14,763
Cost:
$33,419
$2,150 49,862 $9,438 694 $3,473 448 $(-298) - $2,150
49,862
kWh
$9,438
694
kW-months/year
$3,473
448
MMBtu
$(-298)
-
$
TOTAL IMPLEMENTED Savings:
$3,848
Cost:
$11,350
$1,211 28,082 $844 62 $2,091 269 $(-298) - $1,211
28,082
kWh
$844
62
kW-months/year
$2,091
269
MMBtu
$(-298)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Electricity Usage Electricity Demand Natural Gas Personnel Changes