IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

13

matching recommendations
Reset
NAICS 112 Animal Production and Aquaculture
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MS0392 # 01 Y:2012 01 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,327 $5,642 Not Implemented
SF0411 # 01 Y:2012 01 2012 COMBINE UTILITY METERS $35,266 $0 Implemented
SF0411 # 02 Y:2012 02 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,097 $504 Implemented
SF0411 # 03 Y:2012 03 2012 SCHEDULE USE OF ELEVATORS TO CONSERVE ENERGY $716 $0 Implemented
SF0411 # 04 Y:2012 04 2012 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,666 $1,200 Implemented
SF0411 # 05 Y:2012 05 2012 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $19,104 $6,660 Not Implemented
SF0411 # 06 Y:2012 06 2012 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $1,094 $939 Implemented
SF0411 # 07 Y:2012 07 2012 USE MULTIPLE-EFFECT EVAPORATORS $14,245 $17,433 Not Implemented
SF0411 # 08 Y:2012 08 2012 RECOVER WASTE HEAT FROM EQUIPMENT $2,723 $3,965 Not Implemented
SF0411 # 09 Y:2012 09 2012 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $4,671 $11,216 Not Implemented
SF0411 # 10 Y:2012 10 2012 INSTALL OCCUPANCY SENSORS $18,497 $47,901 Implemented
SF0411 # 11 Y:2012 11 2012 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $1,227 $3,774 Not Implemented
SF0411 # 12 Y:2012 12 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $33,986 $135,330 Implemented