Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
519
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0207 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,473 | $13,820 | Not Implemented |
IC0207 # 04 Y:2018 | 04 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,736 | $7,996 | Not Implemented |
IC0207 # 03 Y:2018 | 03 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,822 | $290 | Not Implemented |
MZ0257 # 12 Y:2018 | 12 | 2018 | MINIMIZE WATER USAGE | $37,478 | $0 | Implemented |
MZ0257 # 11 Y:2018 | 11 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,204 | $0 | Not Implemented |
MZ0257 # 10 Y:2018 | 10 | 2018 | USE COMPRESSOR AIR FILTERS | $222 | $200 | Implemented |
MZ0257 # 09 Y:2018 | 09 | 2018 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $1,294 | $5,330 | Implemented |
MZ0257 # 08 Y:2018 | 08 | 2018 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $839 | $1,900 | Implemented |
MZ0257 # 07 Y:2018 | 07 | 2018 | USE OPTIMUM THICKNESS INSULATION | $7,678 | $7,480 | Implemented |
MZ0257 # 06 Y:2018 | 06 | 2018 | INSULATE BARE EQUIPMENT | $600 | $752 | Implemented |
MZ0257 # 05 Y:2018 | 05 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,826 | $0 | Implemented |
MZ0257 # 04 Y:2018 | 04 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,225 | $1,800 | Implemented |
MZ0257 # 03 Y:2018 | 03 | 2018 | INSTALL OCCUPANCY SENSORS | $1,472 | $3,025 | Not Implemented |
MZ0257 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $869 | $5,414 | Not Implemented |
MZ0257 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $490 | $2,925 | Not Implemented |
IC0200 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,021 | $2,210 | Not Implemented |
IC0200 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $263 | $30 | Not Implemented |
IC0200 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,321 | $1,626 | Not Implemented |
IC0200 # 04 Y:2018 | 04 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,064 | $2,230 | Not Implemented |
IC0200 # 05 Y:2018 | 05 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,255 | $3,131 | Not Implemented |
IC0200 # 06 Y:2018 | 06 | 2018 | UPGRADE CONTROLS ON COMPRESSORS | $1,524 | $2,139 | Not Implemented |
BD0493 # 08 Y:2016 | 08 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $188 | $500 | n/a |
BD0493 # 07 Y:2016 | 07 | 2016 | INSTALL OCCUPANCY SENSORS | $925 | $1,050 | n/a |
BD0493 # 06 Y:2016 | 06 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $932 | $20 | n/a |
BD0493 # 05 Y:2016 | 05 | 2016 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,280 | $50 | n/a |