Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
27
matching recommendationsNAICS | 311224 | Soybean and Other Oilseed Processing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0532 # 06 Y:2019 | 06 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,025 | $8,491 | Implemented |
SF0532 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $950 | $2,757 | Implemented |
SF0532 # 04 Y:2019 | 04 | 2019 | INSULATE BARE EQUIPMENT | $1,777 | $4,972 | Not Implemented |
SF0532 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $2,762 | $4,681 | Not Implemented |
SF0532 # 07 Y:2019 | 07 | 2019 | REPLACE BOILER | $20,414 | $108,576 | Implemented |
SF0532 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,844 | $20,718 | Implemented |
SF0532 # 01 Y:2019 | 01 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $879 | $0 | Implemented |
SF0530 # 02 Y:2018 | 02 | 2018 | UPGRADE CONTROLS ON COMPRESSORS | $13,070 | $22,633 | Implemented |
SF0530 # 08 Y:2018 | 08 | 2018 | USE SOLAR HEAT TO MAKE ELECTRICTY | $97,224 | $532,260 | Not Implemented |
SF0530 # 07 Y:2018 | 07 | 2018 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $14,120 | $58,070 | Implemented |
SF0530 # 06 Y:2018 | 06 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $209 | $564 | Implemented |
SF0530 # 05 Y:2018 | 05 | 2018 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,743 | $4,357 | Implemented |
SF0530 # 04 Y:2018 | 04 | 2018 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $5,255 | $11,220 | Implemented |
SF0530 # 03 Y:2018 | 03 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $47,808 | $97,552 | Implemented |
SF0530 # 01 Y:2018 | 01 | 2018 | INSTALL TIMERS AND/OR THERMOSTATS | $6,177 | $2,407 | Implemented |
SF0508 # 06 Y:2017 | 06 | 2017 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $1,181 | $6,155 | Not Implemented |
SF0508 # 05 Y:2017 | 05 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,954 | $26,825 | Implemented |
SF0508 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,172 | $20,431 | Not Implemented |
SF0508 # 03 Y:2017 | 03 | 2017 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $640 | $553 | Not Implemented |
SF0508 # 02 Y:2017 | 02 | 2017 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $20,198 | $2,023 | Implemented |
SF0508 # 01 Y:2017 | 01 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,154 | $0 | Implemented |
SF0501 # 01 Y:2017 | 01 | 2017 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,520 | $0 | Implemented |
SF0501 # 05 Y:2017 | 05 | 2017 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $2,356 | $1,821 | Not Implemented |
SF0501 # 04 Y:2017 | 04 | 2017 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $7,074 | $1,769 | Implemented |
SF0501 # 03 Y:2017 | 03 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $777 | $84 | Not Implemented |